Blacklisting of contractor
Blacklisting of contractor legal meaning, translation and judicial precedents.
Meaning & Judicial Interpretation: (اردو مفہوم اور قانونی تشریح)
Procuring agency was competent to permanently or temporarily bar the supplier and contractor from participating in its procurement proceedings who failed to provide satisfactory performance or were found to be indulged in corrupt or fraudulent practice
Such supplier or contractor should be afforded adequate opportunity of hearing before blacklisting
Procuring agency could devise manner and mechanism to arrive at an inference for such decision which should base on some material and cogent reasons
Proceedings were conducted before the Standing Committee against the petitioner-contractor and he was given proper opportunity of hearing
No illegality was pointed out in the impugned order
Procuring agency could not be compelled to do business with a specific contractor and supplier
Decision to debar permanently or temporarily a contractor and supplier to participate in the procurement proceedings should depend upon the severity of alleged offence
Principles of natural justice and proportionality should be taken into consideration while awarding a punishment to a contractor for his malfeasance
Petitioner-contractor in the present case, had been permanently debarred from venturing into contractual obligations
Nothing was on record as to whether petitioner-contractor acted or omitted to act in collusion with other alleged culprits, the profits it gained and loss was suffered by the procuring agency
Permanently blacklisting the petitioner-contractor was harsh and heavy punishment in the present case
No right of appeal had been provided to the petitioner-contractor
Party affecting from an adversarial order should have right to challenge the same before the higher forum
If such right was abridged then there would be miscarriage of justice
High Court could examine such order on the touchstone of natural justice
Matter was remanded to the competent authority for decision afresh within a specified period
Constitutional petition was disposed of in circumstances.
Petitioner company was aggrieved of decision made by authorities blacklisting it for a period of three years-Validity-Blacklisting of a contractor or supplier under R.19 of Punjab Procurement Rules, 2009, entailed serious consequences of forbidding contractor/supplier from participating in future tenders, which would not only result in deprivation from its business activities but amounted to commercial killing of the company
Blacklisting also tarnished its reputation, credibility and honour in business community, therefore, such disaster step of blacklisting of contractor/supplier could not be resorted to without observing fair trial and due process of law as envisaged in Arts.4 & 10-A of the Constitution
Words 'mechanism' and 'manner' used in R.19 of Punjab Procurement Rules, 2009, were not meaningless rather it denoted due process and fair procedure which included adjudication by impartial and independent authority, prescribing fair criteria, proportionate duration of punishment and structuring of discretion of authorities exercising power of blacklisting
Word 'shall' used in R.19 of Punjab Procurement Rules, 2009, also made it mandatory and obligatory for procuring agency to provide such fair and transparent mechanism and manner of blacklisting-petitioner was initially blacklisted for a period of three years on 31-10-2012 and remained blacklisted for almost 16 months till date when the' case was remanded with consent of parties on 11-2-2014
On remand while passing order dated 4-4-2014, the period during which petitioner already remained blacklisted was not excluded and petitioner was again blacklisted for another period of three years, which amounted to double jeopardy in clear violation of Art.13 of the Constitution
Contractor could be blacklisted who had consistently failed to provide satisfactory performance
Prior to contract in question, petitioner had not defaulted in any other previous contract relating to authorities-In absence of failure to provide satisfactory performance in any other contract, it could not be said that petitioner had consistently failed to provide satisfactory performance-Order of blacklisting was not within the parameters of R. 19 of Punjab Procurement Rules, 2009-High Court in exercise of Constitutional jurisdiction set aside the order passed by authorities blacklisting the petitioner
Petition was allowed accordingly.
Administrative compulsion and wisdom to structure discretion as in R.19 of Punjab Procurement Rules, 2009, is to remove human subjectivity from exercise of discretion
Constitutional and jurisprudential importance of structured discretion is that it nursed requirement of due process, fairness and fair trial and safeguards unbridled discretion against voice of discrimination and arbitrariness.
Administrative compulsion and wisdom to structure discretion as in R.19 of Punjab Procurement Rules, 2009, is to remove human subjectivity from exercise of discretion
Constitutional and jurisprudential importance of structured discretion is that it nursed requirement of due process, fairness and fair trial and safeguards unbridled discretion against voice of discrimination and arbitrariness.
Blacklisting of a contractor or supplier under R.19 of Punjab Procurement Rules, 2009, entailed serious consequences of forbidding contractor/supplier from participating in future tenders, which would not only result in deprivation from its business activities but amounted to commercial killing of the company
Blacklisting also tarnished its reputation, credibility and honour in business community, therefore, such disaster step of blacklisting of contractor/supplier could not be resorted to without observing fair trial and due process of law as envisaged in Arts.4 & 10-A of the Constitution
Words 'mechanism' and 'manner' used in R.19 of Punjab Procurement Rules, 2009, were not meaningless rather it denoted due process and fair procedure which included adjudication by impartial and independent authority, prescribing fair criteria, proportionate duration of punishment and structuring of discretion of authorities exercising power of blacklisting
Word 'shall' used in R.19 of Punjab Procurement Rules, 2009, also made it mandatory and obligatory for procuring agency to provide such fair and transparent mechanism and manner of blacklisting
Petitioner was initially blacklisted for a period of three years on 31-10-2012 and remained blacklisted for almost 16 months till date when the case was remanded with consent of parties on 11-2-2014
On remand while passing order dated 4-4-2014, the period during which petitioner already remained blacklisted was not excluded and petitioner was again blacklisted for another period of three years, which amounted to double jeopardy in clear violation of Art.13 of the Constitution
Contractor could be blacklisted who had consistently failed to provide satisfactory performance
Prior to contract in question, petitioner had not defaulted in any other previous contract relating to authorities
In absence of failure to provide satisfactory performance in any other contract, it could not be said that petitioner had consistently failed to provide satisfactory performance
Order of blacklisting was not within the parameters of R. 19 of Punjab Procurement Rules, 2009
High Court in exercise of constitutional jurisdiction set aside the order passed by authorities blacklisting the petitioner
Petition was allowed accordingly.
Procuring agency is required to prescribe method and system for dealing with complaints against contractors and suppliers for their temporary and permanent blacklisting.
"Blacklisting of contractor", Pakistan Law Portal, available at: https://paklawportal.com/words-terms-maxims/124952851
Precedents & Case Laws citing "Blacklisting of contractor"
P L D 2015 Lahore 34
Messrs HABIB RAFIQ PVT. LTD. Through Authorized Representative — Petitioner Versus GOVERNMENT OF PUNJAB and another — Respondents
Court: High Court2015 C L D 72
Messrs HABIB RAFIQ PVT. LTD. through Authorized Representative — Petitioner Versus GOVERNMENT OF PUNJAB through Chief Secretary and another — Respondents
Court: LahoreP L D 2006 Lahore 84
Messrs M.A. ALEEM KHAN through Chairman — Petitioner Versus PROVINCE OF THE PUNJAB through Secretary, Communication and Works Department, Lahore and 4 others — Respondents
Court: High Court2016 Y L R 296
SHEHZAD ALAM — Petitioner Versus SECRETARY, HOUSING AND PHYSICAL PLANNING and others — Respondents
Court: Lahore1997 C L C 1475
TRISTAR SHIPPING LINES LIMITED‑‑‑Petitioner Versus GOVERNMENT OF PAKISTAN through Secretary,
Court: LahoreP L D 2016 Sindh 398
PACIFIC EXIM (PVT.) LTD. through Company Secretary — Petitioner Versus PAKISTAN STEEL MILLS CORPORATION through Chairman and another — Respondents
Court: High Court2014 S C M R 1748
Messrs KULJA INDUSTRIES LIMITED — Appellant Versus CHIEF GENERAL MANAGER, W.T. PROJECT, BSNL and others — Respondents
Court: Supreme Court of India2021 C L C 472
Messrs TAJ MEDICOS through Proprietor — Plaintiff Versus PUBLIC PROCUREMENT REGULATORY AUTHORITY through Chairman/Managing Director and 5 others — Defendants
Court: Sindh2021 C L C 337
MUSAWAR KAMAL — Petitioner Versus SECRETARY, MINISTRY OF PETROLEUM AND NATURAL RESOURCES, GOVERNMENT OF PAKISTAN and 5 others — Respondents
Court: Islamabad2019 Y L R 524
Messrs SHAHEEN AND SONS GOVERNMENT CONTRACTOR through Managing Director (MD) — Petitioner Versus PROVINCIAL GOVERNMENT through Chief Secretary, Gilgit-Baltistan and 6 others — Respondents
Court: Gilgit-Baltistan Chief Court