2017 CLC 966 KARACHI-HIGH-COURT-SINDH Judicial Precedent
Scope"License" and "easement"Distinction

"License" was a personal privilege to do some particular act or series of acts on the land without possessing any estate or interest therein, and was ordinarily revocable at the will of licensor and is not assignable

License was not a contract between licensor and licensee but a mere personal permit therefore a license was distinguishable from an "easement" which implied an interest in the land and a "lease" or right to take profits of land

License with respect to property was a privilege to go on premises for a certain purpose, but did not operate to confer on, or vest in, licensee any title, interest, or estate in such property.

2016 CLC 1304 ISLAMABAD Judicial Precedent
Ss. 15 & 28Generation licenseSuspension and revocationAnnual generation license fee

Petitioner company was granted generation license but it failed to fulfill the requirements of the agreement, thus did not generate electricity

Authorities issued notice to petitioner for recovery of annual generation license fee

Validity

When name of petitioner company was withdrawn from the list of projects, it was not possible for them to continue their business and make payment towards license fee

Imposition of fine was to be assessed, if they would have continued their operation or construction

Action initiated by authorities against petitioner was contrary to law and legal aspect with regard to invoke S.28 of Regulation of Generation, Transmission and Distribution of Electric Power Act, 1997 was grossly ignored by the Authority

Initiation of proceedings and onward superstructure built on passing any other orders including review was uncalled for and not sustainable under law

National Electric Power Regulatory Authority should have considered for invoking S.28 of Regulation of Generation, Transmission and Distribution of Electric Power Act, 1997 thereby revocation order suspending license should have been passed in view of prevailing circumstances as pointed out by petitioner company in its letters communicated time to time and responding notices and other proceedings initiated

Constitutional petition was allowed in circumstances.

Sponsored Content / تشہیری مواد
How to cite this page: "Generation license", Pakistan Law Portal, available at: https://paklawportal.com/words-terms-maxims/124957039

Precedents & Case Laws citing "Generation license"

CLC 2020
2019-April-18

2020 C L C 173

NATIONAL ELECTRIC POWER REGULATORY AUTHORITY, ISLAMABAD — Appellant Versus GUJRANWALA ENERGY (PVT.) LIMITED — Respondent

Court: Islamabad
CLC 2016
2016-April-18

2016 C L C 1304

GUJRANWALA ENERGY LIMITED — Petitioner Versus NATIONAL ELECTRIC POWER REGULATORY AUTHORITY (NEPRA) — Respondent

Court: Islamabad
PLD 2021
2021-July-8

P L D 2021 Islamabad 221

ISLAMABAD ELECTRIC SUPPLY COMPANY LIMITED through Additional Director General Legal — Petitioner Versus NATIONAL ELECTRIC POWER REGULATORY AUTHORITY and others — Respondents

Court: High Court
PLD 2017
2016-August-18

P L D 2017 Sindh 73

OLYMPIA POWER GENERATION (PVT) LTD. through Chief Executive Officer and another — Appellants Versus SUI SOUTHERN GAS COMPANY LTD. — Respondent

Court: High Court
PLD 2016
2015-September-2

2016K46

AGAR TEXTILES (PRIVATE) LTD. through Authorised Officer — Petitioner Versus FEDERATION OF PAKISTAN through Secretary, Ministry of Water and Power, Islamabad and 2 others — Respondents

Court: High Court
CLC 2017
2017-May-9

2017 C L C 1259

ACCESS SOLAR (PVT.) LTD. and 2 others — Petitioners Versus FEDERATION OF PAKISTAN and 3 others — Respondents

Court: Islamabad
CLC 2021
2016-April-14

2021 C L C 959

NISHAT CHUNIAN POWER LIMITED through Managing Director and others — Petitioner Versus FEDERATION OF PAKISTAN through Ministry of Water and Power Islamabad and 2 others — Respondents

Court: Islamabad
CLC 2016
N/A

2016 C L C 1805

HIGH FLYING SOLAR DEVELOPMENT PAKISTAN LTD. and others — Petitioners Versus NATIONAL ELECTRIC POWER REGULATORY AUTHORITY and others — Respondents

Court: Islamabad
PLD 2017
Suits Nos. 1145 to 1150 and 1263, 1307 of 2008, 367, 1616, 1783 of 2014, 192 and- 572 of 2015, decided on 30th June, 2015.

P L D 2017 Sindh 520

Messrs BHANERO ENERGY LTD. and others — Plaintiffs Versus SUI SOUTHERN GAS CO. LIMITED — Defendant

Court:
SCMR 2019
Civil Petitions Nos. 3186 and 3187 of 2017, decided on 22nd October, 2018.

2019 S C M R 101

SPACE TELECOM (PRIVATE) LIMITED, LAHORE — Petitioner Versus PAKISTAN TELECOMMUNICATION AUTHORITY, ISLAMABAD through Chairman — Respondent

Court: Supreme Court of Pakistan