Breach of Contract
Breach of Contract legal meaning, translation and judicial precedents.
Meaning & Judicial Interpretation: (اردو مفہوم اور قانونی تشریح)
Complainant was advocate and accused was his client who paid professional charges in shape of cheque which was dishonoured on presentation
Held: If client failed to make full fee payment, the amount could be recovered through civil remedies
Initiation of criminal case against one's own client could only be considered in exceptional circumstances where no other remedy was available
Failure to pay for service, such as legal representation, does not necessarily result in penal consequences
State of consciousness that is culpable is the essential component of criminal liability
Dishonestly issuing a cheque is punishable with up to three years' imprisonment under section 489-F, P.P.C. and the offence necessitates rigorous examination
Alternative remedies were available under civil law, such as claim for compensation for loss or injury resulting from breach of contract under section 73 of Contract Act, 1872 and suit for recovery under Civil Procedure Code, 1908
Provision of section 489-F, P.P.C. is intended to function as a safeguard against fraud, rather than as a blade to enforce civil recovery
Mens rea (dishonest intent) must be established in order to incur penal consequences and criminal proceedings under 489-F, P.P.C. must not be used as a substitute for civil remedies
Bail was allowed.
Onus to prove damages
Respondent/plaintiff was employee of appellant/Company who sought recovery of general and special damages early retirement from service on the plea of being penalized wrongly
Trial Court decreed the suit in favour of respondent/plaintiff
Validity
Respondent/plaintiff need not have led any special evidence to quantify damages in lieu of pain and suffering as they were damages that could not be quantified by reducing them to a financial number
Damages in lieu of pain and suffering fall within the category of general damages
Once respondent/ plaintiff established through evidence wrongful conduct of appellant/ company that would naturally have caused pain and suffering
It was for Court to determine quantum of damages that would be compensatory in nature and satisfy conscience of Court that respondent/plaintiff as claimant had been duly compensated for bearing such pain, suffering and agony inflicted on him
High Court declined to interfere in judgment and decree passed by Trial Court
High Court directed appellant/company to pay interest on decretal amount from the date of judgment until the day when such amount was paid by appellant/ company to respondent/plaintiff
Appeal was dismissed, in circumstances.
High Court while exercising its constitutional jurisdiction cannot settle the terms and conditions of a contract between the parties, nor can it direct the Executive to incorporate or omit any specific stipulation therein, as such matters fall exclusively within the domain of the Executive
It is equally well-established that in matters concerning the enforcement of contractual obligations, High Court ordinarily refrains from exercising constitutional jurisdiction to enforce the terms and conditions of the contract and/or to provide a remedy for its breach
The constitutional jurisdiction of the High Court cannot be ousted, especially where an element of perversity or patent illegality is prima facie apparent on the face of the record
It is a recognized principle of law that albeit the constitutional jurisdiction should not be exercised ordinarily in matters arising out of breach of contract, however, an exception exists where the breach has been committed by the Government, a semi-Government body, or a Local Authority, necessitating the resolution of intricate and disputed legal questions
In such circumstances, the grievance may appropriately be addressed through the exercise of jurisdiction under Art. 199 of the Constitution.
Damages are costs that are imposed not as a deterrent or as a means to punish person(s) or party(s) who has/have breached a contract but instead to bring the person(s) or party(s) who has/have suffered from the breach of contract into a position which they would have been had the breach of contract not accrued
Said principle is known as the principle of restitutio in integrum (restoration to original condition)
It therefore stands to reason that damages are in fact the compensation that the law awards when a breach of contract occurs as compensation for the loss that a person or party has suffered from a breach of contract.
Onus would lie on a plaintiff or claimant to prove that there had been a contract entered into between the parties; that there had been a breach of contract; and the extent of the damages claimed thereof.
However, the nature of general and special damages and proving the two are different compared to each other.
Damages are costs that are imposed not as a deterrent or as a means to punish person(s) or party(s) who has/have breached a contract but instead to bring the person(s) or party(s) who has/have suffered from the breach of contract into a position which they would have been had the breach of contract not accrued
Said principle is known as the principle of restitutio in integrum (restoration to original condition)
It therefore stands to reason that damages are in fact the compensation that the law awards when a breach of contract occurs as compensation for the loss that a person or party has suffered from a breach of contract.
However, the nature of general and special damages and proving the two are different compared to each other.
Onus would lie on a plaintiff or claimant to prove that there had been a contract entered into between the parties; that there had been a breach of contract; and the extent of the damages claimed thereof.
Claim of the plaintiffs was that the defendants (appellants) had entered into a contract whereby they had assured to get them performed Hajj against the money, so obtained by the defendants but they failed to arrange Hajj visas
Defendants had never denied the claim of the plaintiffs rather had admitted the claim to such extent with further claim to have paid such amount to a company
Nothing was produced on record that such deposit was permissible as per contract between parties or was with consent of plaintiffs
In absence thereof, such plea could not help the defendants in escaping their liabilities to honour the contract as well as compensation for breaching the same within the meaning of Contract Act, 1872
Defendants had only applied for quota which was never granted to them yet they not only took amount from the people, including plaintiffs in name of 'getting such persons performed Hajj'
Performing Hajj is normally the greatest desire of a Muslim who, for his life, prays and gathers money for such purpose, therefore, when a person with complete satisfaction of performing Hajj is denied by the contractor (travel agency), the mental shock and agony is inevitable
Defendants being Directors of the company could not escape their liabilities towards the company
Appeal was dismissed.
Accused had entered into an agreement in the year 2019 regarding some orchid for harvesting and marketing different fruits for a period of three years; he had paid the amount for the first year and some amount for second year but he could not pay the remaining amount for subsequent period and dishonoured cheques pertained to that unpaid amount
Contention of accused that the date of agreement was tampered with was substantiated from the fact that agreement was shown to be executed in the year 2019 while some of the cheques were shown to be handed over to the complainant having dates of the years 2017 and 2018
Business relation between the parties was admitted regarding which an admitted agreement was also available on record and it appeared that the matter was a case of breach of contract
Complainant had not filed a civil suit for rendition/ settlement of accounts
Maximum punishment in the present case was three years, as such, it did not fall under the prohibitory clause of S.497, Cr.P.C.
Accused was admitted to bail, in circumstances.
Landlords filed suit for recovery of price of articles which were removed by the tenant while handing over possession of the suit property
Trial court decreed the claim to a certain extent
Validity
Landlords had to first prove that at the time of handing over possession of the property on rent, said articles were installed and handed over to the tenant
Trial Court had erred in law while holding that the tenant had failed to prove that the articles belonged to him, hence, he had no right to remove the same and as such liable to pay price so that the landlords be compensated
Landlords had not alleged that at the time of handing over the possession of the suit property on rent to the tenant said articles were installed
Revision petition was allowed, concurrent findings of the courts below were set aside and the suit was dismissed, in circumstances.
Suit was decreed with the direction to the executant of agreement to sell to execute conveyance deed in favour of plaintiff but no relief of possession was extended
Validity
Plaintiff had paid all the consideration amount to the defendant/builder of housing society
Defendant had sold suit land in favour of subsequent purchaser and he was bound to refund amount so realized by him to the plaintiff
Builder had failed to complete construction by due date and even he had not returned consideration amount received by him to the plaintiff
Subsequent purchaser had possession of suit property and its sale deed
Execution of conveyance deed through Court in favour of plaintiff would render sale deed in favour of defendants as ineffective
Case of plaintiff for specific performance against the builder had been made out but it had become a case of hardship for the subsequent purchaser
Relief of specific performance, even if contract was enforceable, was discretionary and same could be withheld by the Court
When Court had concluded that grant of relief of specific performance had been made out but it would be a case of hardship to other side or unfair and inequitable to any third party who was not at fault then it should compensate the plaintiff
Builder had breached contract and only execution of title document was not specific performance of a contract of sale of immovable property when plaintiff was not in possession of suit premises
Execution of title document had to be coupled with delivery of possession of suit property to the plaintiff
Court could not grant decree of possession of suit property to the plaintiff owing to the presence of bona fide purchaser of suit premises
Plaintiff should have been granted relief of specific performance with additional compensation, in circumstances
Court in suit for specific peformance could grant two decrees of compensation combined in one judgment in a suit for specific performance
Order of specific performance might be substituted with compensation for it with additional compensation for breach of contract
High Court observed that court, in the present case, should have passed an adequate decree of compensation both as substitution of specific performance and additional compensation for breach of contract
Decree of specific performance of an agreement to sell through execution of title document against the builder in favour of plaintiff was in the field with no result and there was likelihood that builder would avoid the said decree
High Court passed order for attachment of movable and immovable property of builder who had received consideration amount from the plaintiff but had not returned the same
Plaintiff was entitled for adequate compensation keeping in view escalation in valuation of suit premises and value of currency which had gone down due to inflation in the country
Property of builder would remain attached till the judgment was executable
Second appeal was allowed accordingly.
In order to succeed in a claim for damages under S. 73 of the Contract Act, 1872, claimant had to prove the same through positive evidence; whereas liquidated damages could only be granted under S. 74 of the Contract Act, 1872 ,when inter alia, an aggrieved party proves default / breach of contract by the other party.
Parties may determine expected losses and agree for an amount to be paid in breach of contract and earnest money was part of purchase price when transaction went forward, and same was forfeited when a transaction fell though by reason of fault and failure of vendee
Discretion, however lay with the Court to interpret and implement a forfeiture clause in an agreement
Court, if forms an opinion, that amount mentioned in an agreement as liquidated damages for breach, penalty or forfeiture; was unreasonable, then it was not necessary to implement such clause
Court was not to permit a party to keep the entire amount if it was exorbitantly high and unreasonably harsh.
Contention was that matter between the parties pertained to civil liability and a civil suit for specific performance of the contract was subjudice continuation of the proceedings was an abuse of process of law
Validity
Criminal cases were decided on the basis of material so collected by the prosecution during the course of investigation and the evidence recorded in the Trial Court and that too, after appraisal of evidence by court in accordance with law applicable thereto
High Court could not assume the role of an investigating agency or of a Trial Court to dilate upon the factual controversies involved in the exercise of its writ jurisdiction
Criminal as well as civil proceedings can be proceeded side by side and mere filing of a suit was not a ground for quashing of FIR
Factual controversies involved in the present case could not be resolved in writ jurisdiction
Constitutional petitions were dismissed in circumstances.
Any party who claims damages on account of breach of contract is required under law to establish contract, breach thereof and extent of damages put forward/claimed in a suit for damages.
Plaintiffs were required to produce the original agreement to sell as primary evidence as well as attesting witnesses of the same
Plaintiffs did not pay any part of the alleged sale consideration to the defendant
Discretionary relief of specific performance could not be grated where a party seeking such relief had itself failed to perform its agreed part of contract or committed breach thereof
Plaintiffs had failed to discharge their burden to prove the sale agreement in circumstances
Defendant had not received any part of the alleged sale consideration and he was not obliged to fulfill any of his obligations thereunder
Impugned agreement to sell had become void for lack of consideration
Plaintiffs did not take any step to deposit the sale consideration in the Trial Court
Courts below had failed to appreciate the important questions of law involved in the present matter
Impugned judgments and decrees passed by the Court were set aside and suit was dismissed
Second appeal was allowed, in circumstances.
Contention of defendant was that plaintiff did not pay the balance sale consideration on or before the date fixed for performance of agreement to sell and same stood cancelled and advance payment had been forfeited
Trial Court directed the plaintiff to deposit the balance sale consideration in the Court but same was not deposited
Validity
Parties had agreed that agreement to sell would stand cancelled if seller refused or buyer defaulted leaving them to claim refund, penalty and forfeiture as the case might be
If court had decided that specific performance ought not to be granted and contract was broken by the defendant then it could award compensation if plaintiff was entitled to it
Plaintiff, in the present case, was not entitled to specific enforcement of sale agreement
Section 29 of Specific Relief Act, 1877 barred the plaintiff from subsequently suing for compensation for breach of contract if his suit for specific performance was dismissed
Questions whether plaintiff was entitled to discretion in the refund of advance payment made and/or compensation for alleged breach by the defendant, and alternatively, whether defendant was entitled to forfeit the advance payment was to be decided being still open
Suit would survive to the extent of compensation, in circumstances.
Plaintiff entered into an agreement to purchase a residential apartment owned by defendant for which earnest money was given at the time of agreement and remaining amount was to be paid on date specified in the agreement
Defendant could not provide documents of suit property till date agreed by parties
Plaintiff filed suit for specific performance of agreement against defendant but same was dismissed by Single Judge of High Court
Validity
Both parties had attempted to shift blame on to the other and had maintained that they were ready to fulfil their respective part of agreement
No notice whatsoever was given by defendant to plaintiff, calling upon him to complete execution and registration of sale deed in his favour by expressing his readiness to perform his part of contract
No provision existed in agreement for its cancellation by either of the parties
By ignoring admission of defendant in respect of agreement to sell, terms and conditions thereof, and in disregard of the fact that defense set up by defendant was never in relation to willingness of plaintiff, rather it was related to plea that time was essence of contract
Division Bench of High Court set aside judgment and decree passed by the Single Judge of High Court and suit was decreed in favour of plaintiff
High Court Appeal was allowed accordingly.
Contract existed between the parties and suit could not be deemed to be a suit on basis of tort nor could Arts. 21, 22 and/or 36 of Limitation Act, 1908 be applied to the same
Suit was for compensation of breach of contract and same was governed by Art. 115 of Limitation Act, 1908 providing limitation of 3 years from date of breach of contract or where there were successive breaches when such breach occurred in respect of which suit was instituted or where breach was continuing when it ceased
Plaintiff instituted suit within 3 years and same was within time
Application was dismissed in circumstances.
Suit earlier filed was dismissed and thereafter another suit was instituted in which plaint was rejected on the ground of res judicata
Plaintiff who was not party in the earlier suits filed suit for enforcement of another agreement to sell for the same suit land but plaint was again rejected on the principle of res judicata
Validity
When subject-matter of the previously instituted suit was not the same and parties were also not the same then principle of res judicata was not applicable
Plaintiff was neither party to the earlier suits nor specific performance of alleged agreement to sell had been prayed
Present suit was not hit by the principle of res judicata
Bar of res judicata would be applicable where issue was raised, determined and decided in the former proceedings between the parties
Earlier suits were not decided on merits in the present case
Principle of res judicata was not applicable in circumstances
Rejection of plaint did not operate as res judicata against the plaintiff in a subsequent suit
Where earlier suit was dismissed as withdrawn then there was no adjudication or determination of the dispute on merits
Principle of res judicata was not applicable where earlier suit was dismissed as withdrawn
Title of suit land did not vest with the defendants in the present case
Plaintiff could not have expected the defendants to transfer rights or title in the suit land which they did not possess
Agreement to sell could only be specifically enforced against a party/vendor who was owner of the property at the time of execution of agreement to sell
Plaintiff had paid earnest money to the defendants and they should not enjoy earnest money and the suit property
Vendor on breach of contract for sale of immovable property was bound to refund the amount of earnest money to the vendee and pay damages for the loss of bargain by paying market value of the property minus the contract price
Plaintiff, in the present case, had not prayed for the award of damages against the defendants
Court had discretion in the matter of granting appropriate relief and grant damages in lieu of specific performance even if plaintiff had not prayed for the same
Plaintiff had no privity of contract with the defendants in the present case
Plaint could only be rejected if all the reliefs claimed were barred by law
Impugned order passed by the Trial Court was set aside
Matter was remanded to the Trial Court to decide the same afresh after having written statement of defendants
Appeal was allowed in circumstances.
Suit for compensation for breach of contract could be filed within three years to be reckoned when contract was breached.
Limitation for performance of contract was three years either from the date fixed for performance or if no such date was fixed, in that case when the plaintiff had notice that performance was refused
Plaintiff served letter on the defendants which was not only acknowledged by the defendants but they also showed inability to pay legal fee in their written statement
Present suit was within time
No illegality or legal infirmity had been pointed out in the impugned judgments passed by the courts below
Revision was dismissed in circumstances.
Contention of plaintiff-employee was that defendant-company had caused financial loss to him by terminating his service contract illegally
Validity
Plaintiff-employee was bound to establish additional assurance or representations made to him by the defendant-company
Nothing was on record apart from the terms and conditions of appointment of plaintiff-employee
Nothing was on record that termination from service had resulted into breach of any assurance or promise
Principle of master and servant was involved in the present case
Only remedy for the plaintiff-employee was to file suit for damages in circumstances
Plaintiff-employee could not ask for restitution of his service in circumstances
Burden to prove his entitlement to the reliefs on the grounds as stated in the plaint was on the plaintiff-employee
Any compensation or damages could not be awarded to the plaintiff-employee for a loss or damage which had been sustained by him indirectly by reason of breach of contract
Plaintiff-employee was bound to show that defendant's action of terminating his service was against the terms and conditions of contract
Plaintiff and defendant were in equal position to choose to terminate service by giving a 30 days written notice in advance or making the payment in lieu thereof
Defendant-company was within the domain to terminate service of plaintiff-employee by resorting to scheme of appointment letter
Defendant-company had not committed any breach of contract in circumstances
Thirty days period contained in the appointment letter was too short for a person to find out a new job in the private sector
Period of 120 days was reasonable within which a person could secure a new job of the same stature in the private sector
Plaintiff-employee was entitled to either 120 days written notice in advance or payment in lieu thereof
Plaintiff-employee had received 30 days salary in lieu of the stipulated notice and other emoluments and deductions
Plaintiff-employee was directed to be paid the salary of remaining 90 days and other emoluments as per his entitlement
Suit was partly decreed accordingly.
General principles for granting compensation when beneficiary alleged breach of contract were regulated by Ss. 73 & 74 of the Contract Act, 1872 and without proving the actual loan even a fixed amount, stipulated as for liquidated damages, did not become automatically payable.
Party could maintain his right to claim damages with reference to a breach of contract but such right would not be available for the party with reference to natural, local or international changes causing effect upon value of the subject of contract particularly when this was not so mentioned in the agreement.
Plaintiff had filed suit on the basis of an oral agreement between him and the other defendant and no specific role had been mentioned in the plaint against the defendant
Main grievance of the plaintiff was against the defendant Company and its officials whereas the defendant was only an estate advisor for said Company
Defendant was not a beneficiary of the alleged oral agreement
Compensation for breach of contract could be claimed from a party which had breached the terms of the agreement
Person who was not a party to contract was neither necessary nor proper party in a suit for damages
High Court set aside order of Trial Court and allowed the defendant's application for striking out his name as defendant in the suit
Revision was allowed, accordingly.
Passing of decree on doctrine of "unjust enrichment" (no one can be permitted to derive benefit from an undue advantage to become unjustifiably enrich at expense of another)
Scope
Plaintiff was bound to prove that defendant was enriched by receipt of a benefit; that such enrichment was at plaintiff's expense; that such enrichment and/or retention of benefit was unjust; and that defendant could legally be compelled to compensate plaintiff
Mere such assertions would not entitle plaintiff for damages without discharging his such legal obligations to prove the same.
Plaintiff had filed suit on the basis of an oral agreement between him and the other defendant and no specific role had been mentioned in the plaint against the defendant
Main grievance of the plaintiff was against the defendant Company and its officials whereas the defendant was only an estate advisor for said Company
Defendant was not a beneficiary of the alleged oral agreement
Compensation for breach of contract could be claimed from a party which had breached the terms of the agreement
Person who was not a party to contract was neither necessary nor proper party in a suit for damages
High Court set aside order of Trial Court and allowed the defendant's application for striking out his name as defendant in the suit
Revision was allowed, accordingly.
Essential principles.
Public procurement contracts are governed by the Public Procurement Regulatory Authority Ordinance, 2002 and- Rules framed thereunder, which is a special law on the subject
Failure of contractor to supply the goods at agreed price according to the schedule of supply may be a breach of contract which may cause delay the main project, therefore, Procuring Agency is obliged under the law to proceed against the contractor for appropriate action including cancellation of contract at his cost and risk in accordance with law
Contractors are not entitled to any claim beyond the scope of contract and law unless it is provided in the contract for payment of extra cost on the basis of acceleration of price if project is not completed within contract period and no such claim is entertdinable without determination of cause of delay or the reason of non-completion of project within time
Extra payment on the basis of acceleration of prices in the normal circumstances is undue favour to the contractors, which amounts misappropriation of government funds on the part of concerned officials, therefore, the officials involved in such matters must face the consequence of criminal charge and also departmental action for misconduct
Supreme Appellate Court observed that Chief Secretary, Government of Gilgit-Baltistan in cases of extra payment at the cost of burden on the exchequer may hold inquiry into the cause of delay or justification of extra payment to a contractor set the law at motion for action in accordance with law.
Certain amount by way of occupancy value required to be paid by the allottees was mentioned in the respective allotment orders
Such orders also contained a provision to the effect that construction on the allotted plot would be raised within a specified period of time and in case of failure to do so, allottee would be liable to pay non-utilization fee
It could be true that the non-utilization fee in the terms of penalty envisaged by clause 25 of the Allotment Regulations, could be theoretically enforceable, but S.74 of the Contract Act, 1872 had contemplated certain pre-conditions to be satisfied
In the first instance there had to be a sum payable, whether by way of penalty or compensation for breach of contract, in the contract itself; and secondly the non-breaching party was entitled only to reasonable compensation, subject to the maximum amount fixed in the contract
Amended clause 25 of the Regulations did not stipulate any amount and in any case the quantum of fee claimed by Authority in certain cases running into millions of rupees was against the occupancy value of a few thousands, could not by any stretch of imagination be deemed reasonable
Amount claimed, in circumstances; could not be lawfully demanded by the Authority
Petitions were allowed to the extent that the demand notices in excess of the amount stipulated under the original contract was valid.
Party claiming damages had to firstly plead and then prove by sufficient, trustworthy, independent and. cogent evidence that the concluded agreement existed between the parties, the other party committed breach of contract, such breach entitled the first party to damages and the foremost factor was quantum of damages
Principles for ascertaining the quantum of general and special damages stated.
Solitary statement of one plaintiff was not sufficient to decree the colossal suit amount as plaintiffs' witness did not state anything about damages
Plaintiffs through his failure to produce evidence totally failed to prove that due to breach of contract they were in fact entitled to damages and to what extent, which were sine qua non for the grant of damages under S.73, Contract Act, 1872
Held, plaintiffs, in circumstances, had not proved that they suffered any loss and also failed to prove, through production of evidence on record, that they were entitled for decree of the total amount claimed in the suit.
Party claiming damages had to firstly plead and then prove by sufficient, trustworthy, independent and cogent evidence that the concluded agreement existed between the parties, the other party committed breach of contract, such breach entitled the first party to damages and the foremost factor was quantum of damages
Principles for ascertaining the quantum of general and special damages stated.
Non-production of evidence by plaintiff to the effect that he, on account of any act and deed of defendant, had suffered claimed loss
Effect
Plaintiff would not be entitled for alleged claim of damages.
Defendant was entitled to be supplied with necessary particulars of his claim.
Breach of contract-Plaintiff's suit decreed against defendant establishment and such decree maintained by the High Court in appeal
Defendant's contention that suit was incompetent because of arbitration clause in the contract, would not prevail inasmuch as such contention was not taken or agitated before Courts below and thus could not be allowed to be raised at the petition stage
Leave refused.
Price of cotton having shot up, defendant not fulfilling its obligation of supplying requisite quantity of cotton and plaintiff purchasing 1000 bales of cotton at the enhanced rate ruling in February 1973 and thus suffering loss
Trial Court, on the admission of defendant's witness regarding prices of cotton, adopting Rs.140 per maund as sale price prevailing on 1-2-1973 to determine quantum of damages and decreeing the suit accordingly
No illegality found to have been committed by Trial Court in forming a basis for working out damages in circumstances of case
Equity also was not in favour of defendant-appellant who had, in view of increase in price, chosen not to supply cotton to plaintiff-respondent-Defendant-appellant, held, must, therefore, compensate plaintiff-respondent in the decretal amount
Appeal dismissed.
Court has to award reasonable compensation not exceeding amount so named in contract.-[Compensation].
Finding of High Court being based on proper appreciation of evidence on record, leave to appeal refused.
S. 73-Breach of contract-No breach of contract committed by respondent transferor in respect of terms of transfer of lane.'-Applicant hence, entitled to force any other terms on respondent- Subsequent decision reducing rate of sale price being applicable to allotments made after allotment of plots to applicant, reduction of rate, held, applicable to future transactions and not to applicant's transaction.
Ss. 54 & 73-Sale of goods-Breach of contract-A's suit against H dismissed by Letters Patent Bench on legal consideration of delivery of shipping documents (i.e. invoice, bill of lading, and policy of insurance) being symbolical of delivery of goods purchased, placing same at buyer's risk and entitling seller to payment of their price-Letters Patent Bench also finding all legal requirements under C. I. F. Contract having been duly fulfilled by H it could not be held responsible for shipment of goods to have any hand in their shipment, or in preparation of various documents-Letters Patent Bench also holding there being no evidence for allegation against H of having made any misrepresentation or played fraud on A-Such findings not shown to be faulty on any account-Suit against H, held, rightly dismissed in circumstances.
73-Breach of contract-Short landing certificates-Short landing certificates containing qualification `said to be' short landed-Supports submission of M. S. Bars being neither weighed nor counted-Legitimate inference drawn from such documents : Bundles neither weighed nor counted at time of discharge and goods discharged not in accordance with marks and packing indicated in Export General Manifest-Large quantity of goods found in loose condition at jetty not examined for purposes of identification-Such fact, held further, deprives short landing certificates of their conclusive nature and survey report prepared at consignees' premises could have no material bearing on question of quantity of goods actually shipped.
S. 73-Breach of contract-Damages-Special Leave to Appeal to - Supreme Court-Damages already paid by appellants to other party, reasonable and in no way excessive-Amount paid as far back as ten years ago-Case, in its peculiar circumstances, held, not fit for examination of question of damages-Order granting leave to appeal recalled Constitution of Pakistan (1973), Art. 185(3).-Damages.
S. 73-Breach of contract-Respondent Railways reserving to itself right to terminate agreements at any time before expiry of contracted period by giving licensee a month's notice without assigning any reason and without being liable to pay any compensation- '' Notices of cancellation of lease served on petitioners by respondent in circumstances unexceptionable-High Court's other finding, viz., petitioners evidently secured space at Railway Station by exercise of pernicious influence through Minister of Railways based on proper evidence-Object of writ petitions, viz., to seek enforcement of contractual rights, held, could not be enforced by resorting to constitutional Jurisdiction of High Court-Constitution of Pakistan (1973), Art 199.-[Contract-Jurisdiction].
Ejectment-All Courts below concurrently finding respondent-landlord reasonably and bona fide intending to demolish existing shop and reconstructing same by amalgamating big own shop with that of his uncle -Landlord's uncle also filing ejectment application against his tenant and such application succeeding in sense of tenant having agreed to vacate premises within a year
Not possible, held, in circumstances, to hold respondent having merely adopted a device to pressurize petitioner into paying higher rent-Provisions of S 12(5) & (5-A), held further, provide sufficient safeguards against adoption of any dishonest device by landlord in such cases.
Ss. 203, 205, 206 & 73 -Principal and agent-Damages-Contract of agency -Termination of agency before expiry of agreed term Damages could be recovered only where such termination without "sufficient reason"-Loss of his reputation by agent-Could be considered "sufficient reason" for putting end to agency on part of principal- Whither there way "sufficient cause"-To be determined by circumstances of each case-Loss of reputation not mentioned in letter of revocation by principal as reason for termination of agency although there had been in fact some loss of reputation of agent on account of police action against him-Loss of reputation, in circumstance, although -may not be relied upon as furnishing "sufficient cause" for withdrawal of agency it nevertheless could be taken into consideration In assessing measure of damages-Breach of contract -Principles guiding Court in determination of measure of damages Compensation is payable for actual loss or damage caused
"Breach of Contract", Pakistan Law Portal, available at: https://paklawportal.com/words-terms-maxims/1450
Precedents & Case Laws citing "Breach of Contract"
1992 P T D 1436
COMMISSIONER OF INCOME-TAX Versus ABBASBHOY A. DEHGAMWALLA and others
Court: Bombay High Court (India)2009 C L D 173
AZIZULLAH SHEIKH and another — Petitioners Versus STANDARD CHARTERED'BANK LTD. — Respondent
Court: Supreme Court of Pakistan1991 S C M R 1436
KHATTAK & CO. — Appellant Versus WAPDA through Chairman WAPDA and another — Respondents
Court: High Court2023 P L C (C
HABIB BANK LIMITED through Attorney Versus MEHBOOB RABBANI
Court: Supreme Court of Pakistan2023 S C M R 1189
HABIB BANK LIMITED through Attorney — Appellant Versus MEHBOOB RABBANI — Respondent
Court: Supreme Court of Pakistan2009 SCMR 276
AZIZULLAH SHEIKH and another — Petitioners Versus STANDARD CHARTERED BANK LTD. — Respondent
Court: Supreme Court of Pakistan2002 C L D 754
DESCON MANUFACTURING‑‑‑Appellant Versus M. TUFIAL‑‑‑Respondent
Court: Lahore2000 M L D 1130
GOVERNMENT OF PAKISTAN — Appellant Versus Messrs AL-FAROOQ ROLLER FLOUR MILLS LTD. — Respondent
Court: Lahore2000CLC215
FEDERATION OF PAKISTAN‑‑‑Appellant Versus Messrs ALFAROOQ FLOUR MILLS LTD. ‑‑‑Respondent
Court: LahoreP L D 1979 Karachi 694
SADRUDDIN-Plaintiff Versus Messrs MITCHELL'S FRUIT FARMS LTD., KARACHI-Defendant
Court: -- Ss. 54 & 73-Breach of contract-Plaintiff denying defendant's allegation of having agreed to reduce quantities of fruits to be supplied for reason of being unable to lift quantities originally stipulated for-Proof of modification of original contract-Onus on defendant but no evidence produced to establish fact-Allegation of repudi ation of contract by plaintiff by refusing to accept deliveries also not proved by any reliable evidence-No notice served by defendants on plaintiff complaining breach of contract by non-acceptance of deliveries-Refusal by plaintiff to accept deliveries made by defendant not even averred in written-statement-Contract, held, neither amended nor rescinded by plaintiff.-Contract.