2012 PLP 1424 (MLD)
NAVEED MERCHANT — Petitioner Versus SAFDAR GONDAL and 4 others — Respondents
| Citation | 2012 PLP 1424 (MLD) |
| Forum / Court | Lahore |
| Bench Members | N/A |
| Parties | NAVEED MERCHANT — Petitioner Versus SAFDAR GONDAL and 4 others — Respondents |
| Primary Law | Civil Procedure Code (V of 1908) |
Q1: What are the key laws and sections cited in 2012 PLP 1424 (MLD)?
This judgment primarily cites: Civil Procedure Code (V of 1908) as referenced in Pakistani case law index.
Q2: Which judicial bench decided the case 2012 PLP 1424 (MLD)?
The case was heard and decided by the Lahore bench comprising: N/A.
Q3: What is the official citation format for this judgment on Pakistan Law Portal?
Cite this legal precedent as: 2012 PLP 1424 (MLD) (NAVEED MERCHANT — Petitioner Versus SAFDAR GONDAL and 4 others — Respondents). Read the full summary and cross-referenced laws free on Pakistan Law Portal.
Laws Cited
Representation
- Aamir Mehmood for Petitioner.
- Bilal Kashmiri for Respondents.
Headnotes / Summary
O. I, R. 10
Contract Act (IX of 1872), S.73
Suit for damages and compensation
Defendant's application for striking out his name as a defendant in the suit was dismissed by Trial Court
Plaintiff had filed suit on the basis of an oral agreement between him and the other defendant and no specific role had been mentioned in the plaint against the defendant
Main grievance of the plaintiff was against the defendant Company and its officials whereas the defendant was only an estate advisor for said Company
Defendant was not a beneficiary of the alleged oral agreement
Compensation for breach of contract could be claimed from a party which had breached the terms of the agreement
Person who was not a party to contract was neither necessary nor proper party in a suit for damages
High Court set aside order of Trial Court and allowed the defendant's application for striking out his name as defendant in the suit
Revision was allowed, accordingly.
Judgment & Decree
CH. SHAHID SAEED, J.
Brief facts of the case are that respondent No.1 filed a suit for recovery of compensation, damages and costs of Rs.21,691,460 against the petitioner and respondents Nos. 2 to
5. Petitioner filed an application under Order I Rule 10 C.P.C. for striking out his name from the array of pleadings on the ground that petitioner is neither a necessary nor a proper party to the suit. The said application of the petitioner was dismissed by the learned trial court vide order dated 4-6-2010. Feeling aggrieved by the said order petitioner has filed the instant civil revision.
2. Learned counsel for the petitioner contends that the order passed by the learned trial court is against law and facts and also based upon surmises and conjectures; that in whole the plaint no specific role has been ascribed to the petitioner against the respondent No.1 and only the grievance of the plaintiff is against respondent No.2 and its officials i.e. respondents Nos. 3 to 5; further argued that petitioner works independently and has nothing to do with the business of the respondent No. 2.
3. On the other hand, learned counsel for the respondents argued that petitioner is a proper and necessary party in the suit because he being the estate advisor of defendant No.1 was the direct beneficiary of the agreement executed between the plaintiff and defendant No.1 and application of the petitioner under Order I Rule 10, C.P.C. filed by the petitioner for striking out his name from the arrays of the parties was rightly dismissed by learned trial court.
4. After hearing the arguments of learned counsel for the parties and perusal of record I find that respondent No.1 filed a suit for recovery of compensation and damages on the basis of some oral agreement which was made between the plaintiff and defendant No.1. No specific role has been mentioned in the plaint against the petitioner. The main grievance of the plaintiff is against the Motorola Company/ respondent No.2 and its officials. From the perusal of plaint it reflects that petitioner was the only Estate Advisor of defendant No.1. He was not the beneficiary of the alleged oral agreement, which was made between the parties. It is settled principle of law that compensation for breach of contract can be claimed from a party to a contract, who has breached the terms of agreement. A person who is not a party to a contract is neither necessary nor proper party in a suit for damages. Reliance can be placed to the case of Province of the Punjab through Secretary, Sports Government of the Punjab and another v. Messrs Qavi Engineers (Pvt.) Ltd. through Director and 2 others (2007 MLD 89) Lahore. It is, therefore, I am of the considered opinion that neither the petitioner is proper nor necessary party in the suit filed by the plaintiff because he has no direct connection with the 'defendant No.1. He was also not the beneficiary of the alleged oral agreement as stated above.
5. For the foregoing reasons, the instant civil revision is allowed and impugned order passed by the learned trial court dated 4-6-2010 is set aside. The application under Order I Rule 10, C.P.C. for striking out the name of the petitioner from the arras of the parties is accepted. K.M.Z./N--28/L Revision allowed.