2009 PLP 108 (CLC)
NETWORK LEASING CORPORATION LIMITED — Plaintiff Versus NSA-CTI CONSORTIUM and 2 others — Defendants
| Citation | 2009 PLP 108 (CLC) |
| Forum / Court | Karachi |
| Bench Members | N/A |
| Parties | NETWORK LEASING CORPORATION LIMITED — Plaintiff Versus NSA-CTI CONSORTIUM and 2 others — Defendants |
| Primary Law | Civil Procedure Code (V of 1908) |
Q1: What are the key laws and sections cited in 2009 PLP 108 (CLC)?
This judgment primarily cites: Civil Procedure Code (V of 1908) as referenced in Pakistani case law index.
Q2: Which judicial bench decided the case 2009 PLP 108 (CLC)?
The case was heard and decided by the Karachi bench comprising: N/A.
Q3: What is the official citation format for this judgment on Pakistan Law Portal?
Cite this legal precedent as: 2009 PLP 108 (CLC) (NETWORK LEASING CORPORATION LIMITED — Plaintiff Versus NSA-CTI CONSORTIUM and 2 others — Defendants). Read the full summary and cross-referenced laws free on Pakistan Law Portal.
Laws Cited
Headnotes / Summary
O. XXXIX, Rr.1 & 2
Award of contract by plaintiff for construction of building to defendant under an agreement
Application under O.XXXIX, Rr.1 & 2, C.P.C. restraining the plaintiffs from raising construction on their project subject matter of the suit and a further direction to the Nazir to take over the project
Contentions of the defendants were that work of construction was stopped when a notice was issued. by the Housing Authority and the defendants kept on asking the plaintiff to remove the objections so that the work of construction could start, however the plaintiffs, instead of removing the objections of the Housing Authority, had itself started work of construction with the sole motive of usurping Rs.60,00,000 extra amount spent by the defendants; that unless the construction was stopped, it would not be possible to ascertain the extent of construction raised by the defendants to support its claim of spending Rs.60,00,000 besides the amount received from the plaintiffs and that suit for recovery had been filed mala fide against the defendants
Held, record reflected that in compliance of order of the court project in question was inspected by an Architect and a detailed report had been placed on record which clearly spelled out the extent of construction at the relevant time, the payment made and also the amount outstanding against the defendants
Apprehension of the defendants that in case the plaintiffs were allowed to carry on the construction, it would not be possible to ascertain as to what extent the defendants had carried out the work of construction, was misconceived, in circumstances; even otherwise since there was no suit for counter claim by the defendants against the plaintiffs for the recovery of any amount, therefore, restraining the plaintiffs from carrying on work of construction of its own project would not serve the ends of justice and would be without cause or purpose.
Judgment & Decree
SAJJAD ALI SHAH, J.
Through this application, the defendants seek an order restraining the plaintiff from raising construction on their project, subject-matter of instant suit, and a further direction to the Nazir to take over the project. Ms. Sofia Saeed Shah, learned counsel for the defendants, has pleaded that the plaintiff has awarded a contract to the defendants for raising construction on the suit project on the terms and conditions as detailed in the construction agreement, dated nil May, 2005 and the defendants were raising construction strictly in accordance with the terms and conditions of the agreement and were paid accordingly. It was contended that work of construction was stopped when a notice was issued by the D.H.A. and the defendant kept on asking the plaintiff to remove the objections so that the work of construction can restart. However, the plaintiff, instead of removing the objection has itself started work of construction with the sole motive of usurping Rs.60,00,000 extra spent by the defendants. It was, therefore, contended that unless the construction is stopped, it will not be possible to ascertain the extent of construction raised by the defendants to support its allegation of spending Rs.60,00,000 beside the amount received from the plaintiff. It was lastly stated that the instant suit for recovery has been malafidely filed against the defendants. On the other hand, Mr. Jam Asif Mehmood, learned counsel for the plaintiff, has contended that there is no dispute that the defendants were awarded work of construction by the plaintiff in accordance with the terms and conditions as incorporated in the agreement dated nil May, 2005 and were paid in accordance with the terms and conditions incorporated in the said agreement. However, a dispute arose between the parties when the defendants raised demand for extra work which demand without any justification was enhanced and therefore, the said demand was rejected. The defendant, thereafter, stopped the work of construction and the plaintiff, in accordance with the terms of agreement, appointed Messrs Bag Associates to continue with the construction and filed the instant suit against the defendants for recovery of overdrawn and expected additional expenditure on account of escalation as well as damages. It was further submitted by the learned counsel that vide order, dated 8-10-2007 this Court had appointed Mr. Moinuddin Ahmed, Deputy Registrar (Judicial) as Commissioner to get the measurement carried out from a qualified Architect, the exercise was carried out and the Architect has filed a report wherein not only the extent of construction is stated but also the extent of extra payment received by the defendants has been specified and therefore, in the circumstances the defendants' apprehension is not only misconceived but frivolous. It was lastly, contended that the instant application has been malafidely filed to forestall the rightful claim of the plaintiff and further to pressurize and extort money and therefore, the application is liable to be dismissed. The record reflects that the compliance of order dated 8-10-2007 the project was inspected by an Architect and a detailed report dated 3-3-2008 has been placed on record which clearly spells out the extent of construction at the relevant time the payment made and also the amount outstanding against the defendants. In the circumstances, the apprehension of the defendants that in case the plaintiffs are allowed to carry out the construction, it will not be possible to ascertain that to what extent the defendants have carried out the work of construction is misconceived. Even otherwise, since there is no suit or counter claim filed by the defendants against the plaintiff for the recovery of any amount, therefore, restraining the plaintiff from carrying on work of construction of its own project would not serve the ends of justice and would be without cause or purpose. In the circumstances, the application is misconceived which is dismissed. M.B.A./N-40/K Application dismissed.