2002 PLP 1269 (SCMR)
TAUSEEF CORPORATION (PVT.) LTD. ‑‑‑Petitioner Versus LAHORE DEVELOPMENT AUTHORITY and others‑‑‑Respondents
| Citation | 2002 PLP 1269 (SCMR) |
| Forum / Court | Supreme Court of Pakistan |
| Bench Members | Qazi Muhammad Farooq, Abdul Hameed Dogar and Khalil‑ur‑Rehman Ramday, JJ |
| Parties | TAUSEEF CORPORATION (PVT.) LTD. ‑‑‑Petitioner Versus LAHORE DEVELOPMENT AUTHORITY and others‑‑‑Respondents |
Q1: What are the key laws and sections cited in 2002 PLP 1269 (SCMR)?
This judgment primarily cites: statutory provisions as referenced in Pakistani case law index.
Q2: Which judicial bench decided the case 2002 PLP 1269 (SCMR)?
The case was heard and decided by the Supreme Court of Pakistan bench comprising: Qazi Muhammad Farooq, Abdul Hameed Dogar and Khalil‑ur‑Rehman Ramday, JJ.
Q3: What is the official citation format for this judgment on Pakistan Law Portal?
Cite this legal precedent as: 2002 PLP 1269 (SCMR) (TAUSEEF CORPORATION (PVT.) LTD. ‑‑‑Petitioner Versus LAHORE DEVELOPMENT AUTHORITY and others‑‑‑Respondents). Read the full summary and cross-referenced laws free on Pakistan Law Portal.
Representation
- Mian Allah Nawaz, Advocate Supreme Court with Muhammad Islam, Advocate‑on‑Record for Petitioner
- Advocate Supreme Court, Muhammad Rashid Ahmed, Advocate Supreme Court with Syed Abul Aasim Jafri, Advocate‑on Record for Respondent No.2.
- Date of hearing: 6th March, 2002.
Headnotes / Summary
(On appeal from the order dated 12‑10‑2001 of Lahore High Court Lahore, passed in F.A.O. No.296 of 2001). Specific Relief Act (I of 1877)‑‑‑ ‑‑‑‑Ss. 56 & 54‑‑‑Arbitration Act (X of 1940), S.20‑‑‑Civil Procedure Code (V of 1908). O.XXXIX, Rr.l & 2‑‑‑Constitution of Pakistan (1973), Art. 185(3)‑‑‑Interim injunction, grant of ‑‑‑Necessary ingredients‑‑‑Loss measurable in terms of money‑‑‑Contract for construction of parking plaza was awarded to the plaintiff‑company‑‑‑Company was required Io complete the construction with its own funds and in lieu thereof would claim ownership of certain areas specified in the contract‑‑‑Authorities terminated the contract and construction raised by the plaintiff was demolished‑‑ Authorities got the plaza designed by another company and construction was completed by the Authorities at a heavy cost‑‑-Plaintiff initially invoked Constitutional jurisdiction of High Court for enforcement of the contract but the same was dismissed‑‑‑Later on suit for specific performance of the agreement was filed but the Trial Court rejected the plaint‑‑‑Lastly application under S.20 of the Arbitration Act, 1940, was filed by the plaintiff‑‑‑All the Courts below declined grant of interim injunction to the plaintiff‑‑‑Validity‑‑‑In view of the changed scenario the plaintiff did not have a prima facie case for the purpose of interim relief‑‑‑Balance of convenience also did not tilt in favour of the plaintiff as possession of the construction made by the plaintiff and the site was taken by the Authorities long ago and the process of leasing out the newly‑constructed parking plaza had already commenced‑‑‑Loss allegedly suffered by the plaintiff was measurable in terms of money‑‑‑Supreme Court declined to grant interim injunction‑‑‑Leave to appeal was refused.
Judgment & Decree
QAZI MUHAMMAD FAROOQ, J.‑‑‑Tauseef Corporation (Pvt.) Limited, Lahore through its Director Asif Mahmood has sought leave to appeal against the order dated 12‑10‑2001 passed by a learned Judge in Chambers of the Lahore High Court in F.A.O. No.296 of 2001 whereby the petitioner's application for grant of interim relief under Order 39, rules 1 and 2 was dismissed.
2. The facts to be noted are that the offer made by the petitioner, a construction company, for construction of Parking Plaza at the area known as D‑Point situated in Rang Mehal, Shah Alam Market, Lahore was accepted by the L.D.A. on 30‑5‑1994. Thereafter, pursuant to a tripartite agreement dated 14‑9‑1995 the execution of the work was taken in hand by the petitioner. According to the agreement the petitioner was required to complete the construction with its own funds and in lieu thereof claim ownership of certain areas specified therein. The petitioner executed the work to the extent of 33% but on 20‑2‑1997 the contract was terminated by the Chief Engineer, TEPA. Feeling aggrieved the petitioner filed a writ petition in the Lahore High Court but it was dismissed on 18‑2‑1998 with the observations that the issue was too contentious to be decided in exercise of Constitutional jurisdiction and in presence of the alternative remedy it will be more appropriate if the jurisdiction of the arbitrators is invoked. The I.C.A. filed by the petitioner was also dismissed on 17‑7‑1998 on the same ground. The petitioner then filed a suit for specific performance of the contract but the plaint was rejected. Meanwhile the L.D.A. took possession of the project, demolished the structure raised by the petitioner and got the Parking Plaza constructed through a firm known as Habib & Sons. The petitioner filed. an application under section 20 of the Arbitration Act and alongwith the same moved an application for grant of temporary injunction. The learned Civil Judge seized of the case granted a temporary injunction on 18‑9‑2001 in the following terms:‑‑ "In the light of the foregoing discourse viewed from whatever angle all the three ingredients for issuance of interim prohibitory injunction do admittedly co‑exist. In virtue of clause 10(l),(iv) of the agreement no portion of the applicant company's right hold can legally be dealt with or based out prior to the settlement of the controversy about the rights, liabilities and duties of the applicant as second party to the agreement through Arbitration as envisaged under clause 28 thereof."
3. The L.D.A. filed F.A.O. No.296 of 2001 against the above order which was allowed by a learned Judge in Chambers of the Lahore High Court and the application for grant of temporary injunction was dismissed.
4. It was contended by the learned counsel for the petitioner with vehemence that the petitioner had completed 33 % work, which has been illegally demolished, and as such the L.D.A. was obliged to earmark a specific portion of the Parking Plaza in its favour. It was further contended that the petitioner had a fair prima facie case, the balance of convenience was also in its favour and it will suffer an irreparable loss if the L.D.A is not restrained from leasing out the Parking Plaza to a third party.
5. The learned counsel for the caveator, on the other hand, contended that the petitioner had failed to establish a prima facie case in as much as the writ petition and I.C.A. filed by the petitioner were dismissed and thereafter the petitioner had filed a suit for specific performance of the contract but the plaint was rejected in that case. The construction raised by the petitioner had been demolished and an altogether new Parking Plaza had been constructed. It was also contended that the balance of convenience was also not in favour of the petitioner and same was the case with regard to the element of irreparable loss.
6. Having considered the rival contentions we find that a case for grant of temporary injunction is not made out. Notwithstanding the fate of the writ petition, the I.C.A. and the suit for specific performance of contract filed by the petitioner the work was not completed by the petitioner and the construction raised by it has admittedly been demolished and a new Parking Plaza, designed by NESPAK, has been constructed at a heavy cost by the L. D. A. In view of the changed scenario it cannot be said that the petitioner has a prima facie case for the purpose of the interim relief prayed for. The balance of convenience also does not tilt in favour of the petitioner as possession of the constriction made by the petitioner and the site was taken by the L.D.A. long ago and the process of leasing out the newly‑constructed Parking Plaza has already commenced. As regards the ingredient of irreparable loss suffice it to say the loss allegedly suffered by the petitioner appears to be measurable in terms of money. For the foregoing reasons the petition is dismissed and leave refused. . Q.M.H./M.A.K./T‑27/S Petition dismissed.