2013 PLP 692 (SCMR)
CHAIRMAN/SECRETARY, MINISTRY OF RAILWAYS, GOVERNMENT OF PAKISTAN, ISLAMABAD — Petitioner Versus AFTAB MEHDI — Respondent
| Citation | 2013 PLP 692 (SCMR) |
| Forum / Court | Supreme Court of Pakistan |
| Bench Members | Nasir-ul-Mulk, Asif Saeed Khan Khosa and Sarmad Jalal Osmany, JJ |
| Parties | CHAIRMAN/SECRETARY, MINISTRY OF RAILWAYS, GOVERNMENT OF PAKISTAN, ISLAMABAD — Petitioner Versus AFTAB MEHDI — Respondent |
| Primary Law | Civil service |
Q1: What are the key laws and sections cited in 2013 PLP 692 (SCMR)?
This judgment primarily cites: Civil service as referenced in Pakistani case law index.
Q2: Which judicial bench decided the case 2013 PLP 692 (SCMR)?
The case was heard and decided by the Supreme Court of Pakistan bench comprising: Nasir-ul-Mulk, Asif Saeed Khan Khosa and Sarmad Jalal Osmany, JJ.
Q3: What is the official citation format for this judgment on Pakistan Law Portal?
Cite this legal precedent as: 2013 PLP 692 (SCMR) (CHAIRMAN/SECRETARY, MINISTRY OF RAILWAYS, GOVERNMENT OF PAKISTAN, ISLAMABAD — Petitioner Versus AFTAB MEHDI — Respondent). Read the full summary and cross-referenced laws free on Pakistan Law Portal.
Laws Cited
Representation
- Syed Anwar Shah, Advocate Supreme Court and Ch. Akhtar Ali, Advocate-on-Record for Petitioner.
- Nemo for Respondent.
- Date of hearing: 19th June, 2012.
Headnotes / Summary
(On appeal from the judgment of the Federal Service Tribunal, Karachi Bench, Karachi, dated 27-2-2011 passed in Appeal No.60(K)CS of 2008).
Imposition of major penalty of removal from service notwithstanding report of inquiry committee
Only "slight lapse" in performance of duty by civil servant
Major penalty modified to minor penalty
Railway Department (petitioner) initiated disciplinary action against Divisional Engineer (respondent) after collapse of a railway bridge
Allegation against Engineer was that he did not take appropriate timely action to protect the bridge and safeguard railway traffic
Four charges were levelled against the Engineer, out of which inquiry committee found only one i.e. abnormal delay in processing proposal for repairs of the bridge
Inquiry committee took note of the fact that engineer made correspondence with the Headquarters regarding poor condition of the bridge and necessity of its repair
Inquiry Committee only blamed the Engineer for not submitting an "urgency certificate" to the Headquarters to indicate urgency for carrying out repair works
Notwithstanding findings of the inquiry committee, competent authority imposed major penalty of removal from service on the engineer
Appeal filed by engineer before Service Tribunal was partially allowed, he was reinstated in service and penalty imposed on him was modified to stoppage of one increment for one year
Engineer did submit proposals to Headquarters for carrying out repairs of the bridge and it was the Headquarters which was, to a great extent, responsible for delay in approving the proposal because of making unnecessary queries
Reports further showed that Engineer did make temporary repairs of the bridge, which remained safe for trains operations during his positing for 12 months and even 17 months after he was transferred out
Only charge found proved by the inquiry committee was Engineer's failure to submit "urgency certificate" to the Headquarters while making proposal for repair of the bridge
Imposition of major penalty on Engineer for such a slight lapse was not understandable
Service Tribunal was justified in modifying the penalty imposed to stoppage of one increment
Petition for leave to appeal was dismissed in circumstances and leave was refused.
Judgment & Decree
NASIR-UL-MULK, J.
The respondent, Aftab Mehdi, was posted as Divisional Engineer, Pakistan Railways, Karachi, in the years 2004 and 2005. The railway bridge between Ran Pethani and Dhabeji Stations on Karachi-Kotri Section collapsed in the month of August, 2006. The Department initiated disciplinary action against the respondent for not taking appropriate timely action to protect the bridge and safeguard railway traffic. An inquiry committee was constituted and the respondent was charge sheeted. The inquiry committee in its report dated 21-4-2007 found the allegations not proved. The competent authority on 24-4-2007 ordered a fresh inquiry by another committee. The first inquiry committee exonerated the respondent of all the four charges whereas the second committee found only one, Charge No.1, proved, of abnormal delay by the respondent in processing the proposal for repairs of the bridge in question. The inquiry committee took note of the correspondence between respondent and the Headquarter regarding proposal made by the former regarding poor condition of the bridge and the necessity of its repair. The committee only blamed the respondent for not submitting "urgency certificate" to the Headquarter to indicate the urgency for carrying out the necessary repair works. On the other three charges the committee held that the respondent was not guilty of not taking appropriate action to protect the bridge or arranging for the required repairs to prevent aggravation of the condition of the foundations. The committee found that the respondent had adequate knowledge of hydrological and hydraulic parameters of the bridges and the engineering knowledge and skill. Notwithstanding such findings, the competent authority after issuing show cause notice to the respondent imposed upon him the major penalty of removal from service. He appealed to the Federal Service Tribunal. His appeal was partially allowed and his penalty was modified to a minor one of stoppage of one increment for one year. He was ordered to be reinstated in service. The Chairman Pakistan Railways has filed this petition for leave to appeal against the judgment of the Federal Service Tribunal.
2. We heard the learned counsel for the petitioner who contended that the respondent was responsible for the maintenance of all the railways bridges within his jurisdiction; that the bridge in question collapsed due to his failure to carry out timely necessary repairs. He contended that notwithstanding the lenient view taken by the inquiry committee, the Competent Authority, after providing hearing to the respondent was satisfied about the gravity of his misconduct and thus awarded him major penalty. That the Competent Authority was not obliged to accept the recommendations of the inquiry committee.
3. We perused both the inquiry reports and have found that the respondent did submit proposals to the Headquarter for carrying out repair of the bridge and it was the Headquarter which was, to a great extent, responsible for delay in approving the proposal due to making unnecessary queries. The reports further show that the respondent did make temporary repairs of the bridge. Further that the bridge remained safe for train operation during the respondent's posting as Divisional Engineer, Karachi for 12 months and even 17 months after he was transferred out. The only charge found proved by the second committee was the respondent's failure to submit "urgency certificate" to the Headquarter while making the proposal for repair of the bridge. We fail to understand the imposition of major penalty on the respondent for such a slight lapse. The Service Tribunal was, therefore, legally justified in modifying the penalty to stoppage of one increment. Neither we find any legal flaw in the impugned judgment nor any question of public importance has been raised on behalf of the petitioner. The petition is, therefore, dismissed and leave declined. MWA/C-1/SC Petition dismissed.