CLC 1988

1988 PLP 171 (CLC)

KADIR BAKHSH & SONS‑‑Plaintiff Versus PROVINCE OF SIND‑‑Defendant

Jurisdiction / Court
Karachi
Decided Date
Suit No. 406 of 1973, decided on 23rd September, 1987.
Honorable Judges
Syed Abdur Rehman, J
Case Reference Summary (AEO Optimized)
Citation 1988 PLP 171 (CLC)
Forum / Court Karachi
Bench Members Syed Abdur Rehman, J
Parties KADIR BAKHSH & SONS‑‑Plaintiff Versus PROVINCE OF SIND‑‑Defendant
💡 Quick Legal QA & Summary / سوال و جواب خلاصہ
Q1: What are the key laws and sections cited in 1988 PLP 171 (CLC)?

This judgment primarily cites: statutory provisions as referenced in Pakistani case law index.

Q2: Which judicial bench decided the case 1988 PLP 171 (CLC)?

The case was heard and decided by the Karachi bench comprising: Syed Abdur Rehman, J.

Q3: What is the official citation format for this judgment on Pakistan Law Portal?

Cite this legal precedent as: 1988 PLP 171 (CLC) (KADIR BAKHSH & SONS‑‑Plaintiff Versus PROVINCE OF SIND‑‑Defendant). Read the full summary and cross-referenced laws free on Pakistan Law Portal.

Representation

  • Date of hearing: 23rd September, 1987.

Headnotes / Summary

(a) Contract Act (IX of 1872)‑‑ ‑‑‑S. 56‑‑Lease to collect toll tax on highway‑‑Decrease in traffic for a few days‑‑Frustration of contract, doctrine of‑‑Doctrine of frustration, held, would apply only, when something unanticipated happened‑‑Such doctrine would not apply to a case where anticipated circumstances took place for which provision had already been made in contract‑‑Where contract was for period of nine months while decrease in traffic was only for a week or at the most for two weeks, such decrease, held, would not render either complete frustration of contract or even material frustration thereof‑‑Plaintiff would not be entitled to amount claimed due to decrease in traffic. Parshoram Das Shankar Das v. Municipal Committee, Batala AIR 1949 East Punjab 301; Krell v. Henry (1903) 2 K B 740; Jaffer Brothers Limited v. Islamic Republic of Pakistan P L D 1978 Kar. 585 and T.O.T. Co. v. Uganda Sugar Company Limited AIR 1945 P C 144 ref. (b) Contract Act (IX of 1872)‑‑ ‑‑‑S. 56‑‑Contract of lease to collect toll tax‑‑Provision in contract for forfeiture of earnest money in case of default in payment of instalments‑‑Two instalments not paid by contractor‑‑Earnest money already deposited by contractor sufficient to meet the amount of defaulted instalments‑‑Effect‑‑Where earnest money was nearly sufficient in itself to discharge unpaid instalments and contractor had also paid, part of such instalments and he had to his credit with defendants, a sum which was more than such unpaid instalments, plaintiff, held, would be entitled to refund of excess amount instead of forfeiture of his earnest money‑‑Suit was decreed to the extent of such excess money lying in deposit with the defendant. Province of West Pakistan v. Messrs Mistri Patel & Co P L D 1969 S C 80 ref. S.M. Sadiq for Plaintiff. G.R. Warsi for Defendant.

Judgment & Decree

(1) As under. (2) As under. (3) Yes. (4) No. (5) No. (6) Yes. (7) No. (8) Suit decreed only for a sum of Rs.10,712.43.

6. REASONS The plaintiff has examined their partner Qassim as Exh. 5 and has produced the lease agreement Exh. 5/1 and correspondence between the parties. as Exhs. 6 to

17. As against this the defendant has examined Allahdino Assistant Engineer Highway as Exh. 18.

7. The facts of the case are not materially disputed. The only dispute in this case is as to whether on account of reduction in traffic for the period of 14 days as alleged by the plaintiff and 8 days as alleged by the defendant there was a frustration of the contract and if so whether the plaintiff was entitled to any remission on that account.

8. Mr. S.M. Sadiq, Advocate for the plaintiff has relied upon section 56 of the Contract Act. This section relates to the discharge of contract. Certain principles and the doctrine of the frustration are embodied in this provision, which reads as under:‑‑ "

56. An agreement to do an act impossible in itself is void.‑‑ A contract do an act which, after the contract to is made, becomes impossible, or, by reason of some event which the promisor could not prevent, unlawful, becomes void when the act becomes impossible or unlawful. Where one person has promised to do something which he knew, or, with reasonable diligence, might have known, and which the promise did not know to be impossible or unlawful, such promisor must make compensation to such promise for any loss which such promise sustains through the non performance of the promise." Mr. S.M. Sadiq then referred to the case of Parshoram Das Shankar Das v. Municipal Committee, Batala reported in A I R 1949 (36) East Punjab

301. The facts of this case were that Batala Municipal Committee leased out tonga stand to Parshoram Das for Rs.500. It was subsequenly found that tongawala instead of using those stands used private stands with the result that Parshoram Das got nothing by way of fees from tongawalas. Municipality did everything in its power to compel the tongawalas to use those stands but it could not succeed. It was held that the contract had become impossible and the plaintiff was entitled to refund of the amount in view of section 56 of the Contract Act. Mr. S.M. Sadiq also relied upon the English case of Krell v. Henry reported in 1903(2) K.B.

740. In this case the defendant had agreed to hire from the plaintiff a flat for two days, on which dates coronation procession had to pass along that route. As the procession did not take place on those days the defendant declined to pay the balance of the agreed rent. It was held that the plaintiff was not entitled to recover the balance of rent fixed by the contract due to contingency which happened afterwards.

9. In my view neither section 56 nor the doctrine of frustration contained therein nor any one of these rulings applies to the present case for two reasons. The first is that it cannot be said that the contract did not make reference to the anticipated circumstances and therefore, the plaintiff was unaware of the risk involved in that contract. Clause (9) of the Contract Act reads as under:‑‑ "

9. No remission or reduction of the amount secured to the lessor under this lease will be made by the lessee in respect of any diminution or reduction of the traffic over the Highway or in the income from the tolls collected under the lease due to any case whatsoever." It is quite clear from the perusal of this clause that the defendant had already warned the plaintiff that no remission will be given to him on account of decrease in the traffic for any cause whatsoever.

10. The doctrine of frustration applies only when something which is unanticipated happens. It does not apply to a case where anticipated circumstances take place for which provision has already made in the contract. The second reason is that this was not a case of either complete frustration of contract or even material frustration of the contract. The contract was for a period of as many as 9 months. The decrease in the traffic was only for 8 days or at the most for the 14 days. The plaintiff has alleged that he had suffered a loss of f Rs.1,47,040 during this period and has furnished a detail of collections of these 14 days. He has not furnished the details of collections of the remaining 8 months and 16 days of the contract period. The presumption is that he had earned much more than the contracted amount during that period. It, therefore, cannot be said that the contract had completely or even materially frustrated on account of this decrease of traffic for a small period of 8 or 14 days. The doctrine of frustration will therefore not be attracted to such a case. Reference in this connection may be made to the case of Banori v. S.K. Shakrullah where it was held that doctrine of frustration only applies if the disturbance goes to the extent of substantially preventing the performance of the whole contract. Interference leaving a considerable part capable of performance will got be an excuse. Same view has been taken by a Division Bench of this Court in the case of Jaffer Brothers Limited v. Islamic Republic of Pakistan reported in P L D 1978 Kar. 585 where it was held as follows:‑‑ "In matter of contract, parties in Pakistan are governed by the Contract Act, 1872 and, the legal position is not different under that Act. In the case of an executory contract, where an uncontemiplated turn of events has occurred which makes further performance impossible or unlawful, the contract becomes frustrated at that point and, the parties are absolved from further performance under it. This is provided in section 56 of the Contract Act. But, if the Court holds that notwithstanding the uncontemplated turn of events, the contract does not become impossible to perform, the parties continue to be bound by the terms of the contract. The Court has no power or discretion to qualify the contract and depart from the express terms thereof in order to apply it to the changed circumstances on the ground that it seems just and reasonable to do so, because the change of circumstances was unforeseen by the parties at the time they entered into the contract or because the performance of the contract has become more onerous. In the present case, the contract had been fully performed and the supplier had been paid the price of the cement stipulated in the contract. It was a fixed price on liner terms, that is, it was agreed that the supplier was to be responsible for payment of stevedoring and lighterage charges. Assuming, as did the arbitrator, that the increase in labour charges awarded by the Industrial Court was not in the contemplation of the parties at the time they entered into the contract, nevertheless, the contract was not frustrated and it continued to bind the parties and, in fact, it was fully performed. The arbitrator was, therefore, not justified in departing from the express terms of the contract by awarding extra stevedoring and lighterage expenses to the supplier, on the ground that had the increase in labour charges been foreseen at the time the contract was concluded, the parties would have made provision for it and that, therefore, it was just and equitable to allow the increase for the supplier." The view of the Privy Council that has been expressed in the case of T .0. T . Co. v. Uganda Sugar Company Limited reported in AIR (32) 1945 P C 144 is to the effect that whether frustration occurs depends on the nature of the contract and on the events which have occurred. In the case under ruling appellant company contracted to supply steel rail group Section to respondent Company, the specification defined precisely what were the goods but did not define the source. It was held that the contract was not frustrated because main source of the steel from which it could come i.e. Germany was closed due to war. There were many other possible sources of 'supply from manufacturers in England, America, Belgium and France besides Germany. I am, therefore, of the clear view that the plaintiff is not entitled to refund of the amount of Rs.1,47,040 on account of the decrease in the traffic for this short period.

11. So far as the question of recovery of last two instalments is concerned, no doubt there was a provision for forfeiture of the earnest money in case there was default in payment of instalments, but it may be pointed out that the earnest money which was to the tune of Rs.2,50,000 was nearly sufficient in itself to discharge the two instalments. Moreover, the plaintiff had also paid Rs.65,000 towards the last two instalments, and had thus to his credit with the defendant a sum, which was more than the last two instalments. Hence it would appear that the plaintiff was entitled, on the contrary, to the refund of excess amount, that is a sum of Rs.10,712.43.

12. Reliance was rightly placed by the counsel for the plaintiff in the case of Province of West Pakistan v. M/s Mistri Patel & Co. reported in P L D 1969 S C 80, where it was held that despite express stipulation in a contract the Court can on equitable principles relieve defaulting buyer from forfeiture of earnest money if circumstances of the case justify such a course. In the present case the plaintiff had successfully carried out all the terms and conditions of the contract and paid all the instalments regularly except the last two instalments. The last two instalments, as already pointed out, 'were nearly equal to the amount of the security deposited. It would be very harsh to the plaintiff if in addition to the forfeiture of security deposit, he was compelled to pay the last two instalments. Hence I am of the clear view that defendant is not entitled to forfeit security and still recover the last two instalments under these circumstances.

13. The result is that the plaintiff's suit is decreed but only to the extent of Rs.10,712.43. The costs of the suit shall be borne by the plaintiff. A . A . / K‑49 / K Suit partly decreed.