MLD 2023

2023 PLP 505 (MLD)

Messrs APLOI (PRIVATE) LIMITED through Authorized Representative — Petitioner Versus FEDERATION OF PAKISTAN through Ministry of Interior, Pakistan Secretariat, Constitutional Avenue, Islamabad and 4 others — Respondents

Jurisdiction / Court
Islamabad
Decided Date
2022-December-19
Honorable Judges
N/A
Case Reference Summary (AEO Optimized)
Citation 2023 PLP 505 (MLD)
Forum / Court Islamabad
Bench Members N/A
Parties Messrs APLOI (PRIVATE) LIMITED through Authorized Representative — Petitioner Versus FEDERATION OF PAKISTAN through Ministry of Interior, Pakistan Secretariat, Constitutional Avenue, Islamabad and 4 others — Respondents
Primary Law (b) Public Procurement Rules, 2004, (a) Public Procurement Rules, 2004, (c) Public Procurement Rules, 2004
💡 Quick Legal QA & Summary / سوال و جواب خلاصہ
Q1: What are the key laws and sections cited in 2023 PLP 505 (MLD)?

This judgment primarily cites: (b) Public Procurement Rules, 2004, (a) Public Procurement Rules, 2004, (c) Public Procurement Rules, 2004, (d) Public Procurement Rules, 2004 as referenced in Pakistani case law index.

Q2: Which judicial bench decided the case 2023 PLP 505 (MLD)?

The case was heard and decided by the Islamabad bench comprising: N/A.

Q3: What is the official citation format for this judgment on Pakistan Law Portal?

Cite this legal precedent as: 2023 PLP 505 (MLD) (Messrs APLOI (PRIVATE) LIMITED through Authorized Representative — Petitioner Versus FEDERATION OF PAKISTAN through Ministry of Interior, Pakistan Secretariat, Constitutional Avenue, Islamabad and 4 others — Respondents). Read the full summary and cross-referenced laws free on Pakistan Law Portal.

Laws Cited

(b) Public Procurement Rules, 2004 (a) Public Procurement Rules, 2004 (c) Public Procurement Rules, 2004 (d) Public Procurement Rules, 2004

Representation

  • Muhammad Ahmad Pansota for Petitioner.
  • Hafiz Ahmad Rasheed, A.A.G. for Respondent No. 1.
  • Afnan Karim Kundi for Respondents Nos. 2 to 5.

Headnotes / Summary

Rr. 33, 38 & 44

Procurement contract

Rejection of bids

Purchase order conditional upon a formal definitive contract

Petitioner was aggrieved of cancellation of tender for the supply, installation, commissioning, support, maintenance and upgradation of servers and software for issuing dematerialized identity cards with cryptographic-hash-based dynamic QR authentication codes

Contention of petitioner was that rejection of the bids could occur only prior to the acceptance of bids (Rule 33); that the petitioner's bid was the most advantageous one (Rule 38) and that the procurement contract had 'come into force' on the date the notice of acceptance of bid vide purchase order was given (Rule 44)

Validity

Rule 33 could not be turned on its head to say that just because a bid could not be rejected after it was accepted, it became mandatory for a procuring agency to proceed with a procurement when it no longer desired to

What R. 33 meant to convey was that, amongst competing bids, if any bid was to be rejected, then that was to be done before any was accepted

Rule 38 was also premised on the ground that procurement was going ahead and clarified that the most advantageous bid was to accepted in that case; it did not mandate that the procurement itself became mandatory for the procurer

Effectiveness of a contract of procurement under R. 44 was subject to the condition "where no formal signing of a contract is required "

Purchase order in the instant case was unequivocally conditional upon a formal definitive contract being signed

Constitutional petition was dismissed.

R. 44

Constitution of Pakistan, Art. 199

Constitutional petition

Maintainability

Procurement contract

Petitioner was aggrieved of cancellation of tender for the supply, installation, commissioning, support, maintenance and upgradation of servers and software for issuing dematerialized identity cards with cryptographic-hash-based dynamic QR authentication codes

Contention of petitioner was that it was not necessary to sign a contract and that the purchase order itself contained the contract

Contention of respondent was that software supply, installation and maintenance contracts went into minute details in relation to the performance of the solution as well as other matters such as on-going maintenance and troubleshooting in the software once installed; that a mere purchase order in itself rarely met the requirements of such contracts and that was why the purchase order was issued subject to a definitive binding contract being signed, which was yet to be signed and that it was a basic legal rule that an agreement to agree did not create a concluded and enforceable contract

Validity

Even if it was assumed for sake of arguments that a contract was concluded when the purchase order was issued, even then the remedy for its breach laid in a suit and not by way of a constitutional petition

Constitutional petition was dismissed.

R. 36

Constitution of Pakistan, Art. 199

Constitutional petition

Maintainability

Procedures of open competitive bidding

Information provided in technical proposal used by procuring agency after cancellation of tender

Petitioner was aggrieved of cancellation of tender for the supply, installation, commissioning, support, maintenance and upgradation of servers and software for issuing dematerialized identity cards with cryptographic-hash-based dynamic QR authentication codes

Contention of petitioner was that his entire information was with the respondent and that the respondent had capitalized on that information to develop the solution in-house

Held, that even if the allegation of the petitioner was assumed to be true it still did not translate into any legal right to be enforced in the constitutional jurisdiction

If the respondent while developing the in-house solution had used any proprietary know-how of the petitioner that constituted intellectual property protected against unauthorized use by the intellectual property laws, then the petitioner had a remedy under such laws

Such contention was denied by the respondent by stating that no protected intellectual property not available in the public domain was received as a consequence of the petitioner's proposal

Constitutional petition was dismissed.

R. 44

Procurement contract

Cancellation of tender

Opportunity of hearing

Scope

Petitioner was aggrieved of cancellation of tender for the supply, installation, commissioning, support, maintenance and upgradation of servers and software for issuing dematerialized identity cards with cryptographic-hash-based dynamic QR authentication codes

Contention of petitioner was that an opportunity of hearing was not given before abandonment of the project by the respondent

Validity

No adverse order against the petitioner was passed for it to be heard first

Petitioner had an expectation of winning the contract, if the project was going ahead, but by no means it could be held that the petitioner by submitting the bid acquired the right that the project must be implemented by respondent using external suppliers

No bidder had an unqualified right for a project to be implemented

Present case was not a case of rejection of a bid, as dressed up by the petitioner, but one of abandonment of an externally sourced project

Constitutional petition was dismissed.

Judgment & Decree

SARDAR EJAZ ISHAQ KHAN, J.

The petitioner is aggrieved by the impugned letter dated 24.08.2022, whereby the respondent NADRA cancelled tender No. 121/2021 for the supply, installation, commissioning, support, maintenance and upgrade of servers and software for issuing dematerialised identity cards with cryptographic-hash-based dynamic QR authentication codes. The reason given in the impugned letter for cancellation of tender is that NADRA for various reasons did not wish to proceed with implementing the suggested solution.

2. Learned counsel states, citing several rules of Public Procurement Rules, 2004 (PPRA Rules), that once the purchase order dated 04.03.2022 was issued to his client, it could not have been withdrawn by NADRA, and that too without giving the petitioner company a right of hearing. He cites Messrs Fast Track v. FIA and others (2021 CLC 1160 Islamabad) in support.

3. Fast Track case was about the delivery of printing, office stationery and office equipment, which per the law report had already been delivered before the tender was cancelled. In the instant case, the project entailed several activities noted above, which could be carried out only once the project commenced, such as installation, commissioning, support, maintenance and upgrade of servers and software. Learned counsel stated on the date this petition was admitted that the software had already been delivered and installed, and that it was useable by NADRA. This statement is vehemently controverted by NADRA's learned counsel, and today the learned counsel for the petitioner no longer insisted on this point. That is to say, Fast Track case is entirely distinguishable from the instant case, in that no part-performance of the contract deliverables by the petitioner is established in this case.

4. On the first date of hearing, the following order was passed: I would not have been inclined to admit this petition, were it not for the submission that the software stands delivered and installed. Issuing the writs of certiorari and mandamus prayed for in this petition will effectively translate into compelling the procurement agency to proceed with a procurement that it for various reasons might not find feasible to do. A Constitutional Court cannot compel a procuring agency to perform a contract when it no longer wishes to, for that would tantamount to specific performance of a software supply contract. The petitioner in such a case is not without remedy, for it can sue for damages. However, given the submission that the purchase order stands part-performed by delivery of the software, I consider it appropriate to issue pre-admission notice to NADRA before deciding this petition.

5. The hearing following the pre-admission notice was held today.

6. Learned counsel for the petitioner refers to the impugned letter, which cites rule 33 of PPRA Rules, to say that under rule 33 rejection of the bids can occur only prior to the acceptance of bids. He then referred to rule 38 to say that the bidder with the most advantageous bid was to be awarded the contract, and that his client's bid was the most advantageous one. Continuing, he cited rule 44 to claim that the procurement contract had 'come into force' on the date the notice of acceptance of bid vide the purchase order dated 04.03.2022 was given to his client.

7. However, the rules cited by the learned counsel for his prayers of certiorari and mandamus are not valid in this case. Rule 33 cannot be turned on its head to say that, just because a bid cannot be rejected after it is accepted, it becomes mandatory for a procuring agency to proceed with a procurement when it no longer desires to. What rule 33 is meant to convey is that, amongst competing bids, if any bid is to be rejected, then that is to be done before any is accepted. Rule 38 is also premised on that the procurement was going ahead, and clarifies that the most advantageous bid was to be accepted in that case; it does not mandate that the procurement itself becomes mandatory for the procurer. The submission premised on rule 44 is answered similarly; in fact, the effectiveness of a contract of procurement under rule 44 from the date the acceptance is given is subject to the condition " where no formal signing of a contract is required ", and the purchase order in the instant case was unequivocally conditional upon a formal definitive contract being signed.

8. Learned counsel for the petitioner's references to the aforesaid PPRA Rules to claim that it was not necessary to sign a contract and that the purchase order itself constituted the contract do not prevail with me. We have to see the nature of the project in question. This was a software supply contract, and it is legend that software supply, installation and maintenance contracts go into minute details in relation to the performance of the solution as well as other matters such as on-going maintenance and troubleshooting in the software once it is installed, and a mere purchase order in and of itself rarely meets the requirements of such contracts. That is why the purchase order was issued by NADRA subject to a definitive binding contract being signed, which was yet to be signed, and it is a basic legal rule that an agreement to agree does not create a concluded and enforceable contract. However, even if it is assumed for the sake of argument that a contract was concluded when the purchase order was issued, even then the remedy for its breach would lie in a suit and not by way of a Constitutional petition.

9. Learned counsel contended next that the entire information of the bidder (whatever that means) is with NADRA, and that NADRA has capitalized on that information to develop the solution in-house. Assuming that to be true, though that may be a sharp practice, if that indeed is the case, but that still does not translate into any legal right to be enforced in the Constitutional jurisdiction. If NADRA while developing the in-house solution uses any proprietary know-how of the petitioner that constitutes intellectual property protected against unauthorised use by the intellectual property laws, then surely the petitioner would have a remedy under such laws. This of course is denied by learned counsel for NADRA, stating that no protected intellectual property not available in the public domain was received by NADRA as a consequence of the petitioner's proposal.

10. The next and final submission was premised on natural justice, in that the learned counsel claims that an opportunity of hearing was not given before the abandonment of the project by NADRA. This submission is not valid. No adverse order against the petitioner was passed for it to be heard first. The petitioner had an expectation of winning the contract, if the project was going ahead, but by no means it can be held that the petitioner by submitting the bid acquired the right that the project must be implemented by NADRA using external suppliers. No bidder has an unqualified right for a project to be implemented. I reiterate that this is not a case of rejection of a bid, as dressed up by the petitioner, but one of abandonment of an externally sourced project, and no right of a bidder is violated if such a project is abandoned for the bidder to be heard before abandonment.

11. In a nutshell, a Constitutional Court will not order mandamus to compel a public procurement agency to implement the project solely for the reason that it has earlier issued a bid acceptance letter. It is not for a Constitutional Court to determine which projects NADRA wishes to implement, and whether it wishes to do so through external sourcing or in-house. Neither the PPRA Rules nor the terms of the tender, and for that matter nor does the law, bind NADRA to enter into and perform a contract unless it is specifically enforceable, and a software supply and maintenance contract is not one. The petitioner's remedy, if any, may lie elsewhere, but it does not lie before this Court in its Constitutional jurisdiction by writs of certiorari and mandamus as prayed for.

12. This petition is dismissed. SA/11/Isl. Petition dismissed.