2012 PLP 1222 (SCMR)
STATE OF HARYANA and others — Appellants Versus Messrs MALIK TRADERS — Respondent
| Citation | 2012 PLP 1222 (SCMR) |
| Forum / Court | Supreme Court of India |
| Bench Members | V.S. Sirpurkar and Cyriac Joseph, JJ |
| Parties | STATE OF HARYANA and others — Appellants Versus Messrs MALIK TRADERS — Respondent |
| Primary Law | (b) Contract Act (IX of 1872), (a) Contract Act (IX of 1872) |
Q1: What are the key laws and sections cited in 2012 PLP 1222 (SCMR)?
This judgment primarily cites: (b) Contract Act (IX of 1872), (a) Contract Act (IX of 1872) as referenced in Pakistani case law index.
Q2: Which judicial bench decided the case 2012 PLP 1222 (SCMR)?
The case was heard and decided by the Supreme Court of India bench comprising: V.S. Sirpurkar and Cyriac Joseph, JJ.
Q3: What is the official citation format for this judgment on Pakistan Law Portal?
Cite this legal precedent as: 2012 PLP 1222 (SCMR) (STATE OF HARYANA and others — Appellants Versus Messrs MALIK TRADERS — Respondent). Read the full summary and cross-referenced laws free on Pakistan Law Portal.
Laws Cited
Representation
- Date of hearing: 17th August, 2011.
Headnotes / Summary
S.5
Revocation of offer before acceptance
Scope
Scope
Bid (offer) made for tender with deposit of bid security
Condition that bid security would be forfeited if bid withdrawn (revoked) during its validity period
Withdrawal of bid within its validity period when it had not been accepted
Bid security could be forfeited, in circumstances
Provincial authorities (appellant), in the present case, invited tenders from interested persons for appointment as agent for collection of toll at a bridge
'M' (respondent) was one of the bidders and under the terms and conditions of the bid, deposited Rs. 2 million as bid security
As per terms and conditions of the bid, 'M' agreed to keep the bid/ offer open for acceptance for up to 90 days; agreed that the bid security would be forfeited should 'M' withdraw or modify its bid during the validity period of 90 days, and also agreed that 'M' would be bound by the communication of acceptance of the bid dispatched within the period of 90 days
Letter of acceptance was issued to 'M', which letter stated that security amount and first instalment had to be deposited within 21 days of the receipt of the acceptance letter, but 'M' failed to do the same
Provincial authorities cancelled and withdrew the letter of acceptance issued to 'M' and forfeited its bid security of Rs. 2 million
'M' filed constitutional petition before the High Court with the contention that before receipt of letter of acceptance, it had sent a letter to the Provincial authorities informing them that 'M' was not interested in the work, therefore, the amount of bid security should be refunded
Constitutional petition was allowed by the High Court, letter of acceptance issued by the Provincial authorities was quashed and it was directed to refund the bid security amount of Rs. 2 million to 'M'
Although 'M' had sent its letter withdrawing the bid (offer) before receipt of the acceptance letter, but 'M' had agreed to keep the bid open for acceptance for up to 90 days
'M' had also agreed that it would be bound by the communication of acceptance of the bid dispatched within the said period of 90 days, therefore, 'M' could not have withdrawn the bid before the expiry of the period of 90 days
Admittedly the acceptance of 'M' bid was communicated to it within the period of 90 days, therefore, 'M' was bound by the said acceptance of the bid, despite its withdrawal
'M' had also agreed that the full value of the bid security would be forfeited, should it withdraw or modify its bid/offer, and since 'M' withdrew its bid/offer in violation of the agreement, the full value of the bid security was liable to be forfeited
Although under the Contract Act, 1872, a proposal/offer could be revoked at any time before its acceptance was complete as against the proposer/offeror, but 'M' in the present case was bound by the agreement to keep the bid/offer open for acceptance for up to 90 days, and he was liable to suffer the consequences if he did not do the same
Under the cover of S.5 of the Contract Act, 1872, 'M' could not escape from the obligations and liabilities of the agreement
High Court was not justified in quashing the acceptance letter of the Provincial authorities and directing them to refund the bid security to 'M'
Appeal was allowed and impugned order of the High Court was set aside. National Highways Authority of India v. Ganga Enterprises and another AIR 2003 SC 3823 and 2003 AIR SCW 4381 ref.
S.5
Revocation of offer before acceptance
Scope
Agreement to keep the offer open for a specific period of time
Penalty for revoking/withdrawing the offer before the end of the specific period of time
Effect
Right to withdraw an offer before its acceptance could not nullify the agreement to suffer any penalty for the withdrawal of the offer against the terms of the agreement.
Judgment & Decree
CYRIAC JOSEPH, J.
Leave granted.
2. This appeal is filed against the judg ment dated 7-7-2009 rendered by a Divi sion Bench of the High Court of Punjab and Haryana in C.W.P. No.2266 of 2009, allowing the said writ petition. The appellants were the respondents in the writ peti tion and the sole respondent herein was the petitioner therein.
3. Facts in brief are stated hereunder:-- On 18-9-2008, the appellant-State of Haryana invited tenders from interested persons for appointment as Entrepreneur/Agent for collection of toll at Toll Bridge over river Yamuna on Karnal-Meerut Road, near U.P. Border. The respondent Messrs Malik Traders was one of the 13 bidders who submitted tenders. As required by the terms and conditions of the Bid, all the bidders, including the respondent, deposited the Bid Security of 20 lakhs in the form of bank guarantee or FDR in favour of the Executive Engineer. Messrs Gaurav Traders who quoted 8,83,30,000 was the high est bidder and the respondent Messrs Malik Traders who quoted 7,97,66,180 was the second highest bidder.
4. As required under the terms and con ditions of the bid, the respondent in para graph 8 of its written offer/bid agreed to keep the bid open for acceptance upto 90 days after the last date of receipt of bid. The respondent also agreed that it shall be bound by the communication of acceptance of the bid dispatched within the aforesaid period of 90 days. In paragraph 10 of the offer/bid, the respondent also agreed that the full value of Bid Security would be for feited without prejudice to any other right or remedy available to the Executive En gineer or his successor-in-office or his rep resentative, should the respondent with draw or modify its bid/offer after the last date and time for the receipt of bids, dur ing the period of bid validity (90 days) or extended validity period.
5. Since Messrs Gaurav Traders was found to be the highest bidder, a letter of accep tance was issued to it on 25-9-2008. How ever, it failed to deposit the security amount and the first instalment as per the letter of acceptance. Therefore, as per Condition No.9.3(B) of the Detailed Notice Inviting Tender (DNIT) and Condition No.6 of the acceptance letter, the Bid Security of 20 lakhs deposited by Messrs Gaurav Traders was forfeited and the letter of acceptance was cancelled and withdrawn vide letter dated 16-10-2008 of the competent author ity. Thereafter, a letter of acceptance dated 26-11-2008 was issued to the respondent Messrs Malik Traders who was the second highest bidder. As per Condition No.6 of the said letter of acceptance, the respon dent was required to deposit the security amount and the first instalment within 21 days from the receipt of the letter of ac ceptance. However, the respondent failed to deposit the security amount and the first instalment as required by the letter of ac ceptance. Hence, vide Memo No.5029, dated 17-12-2008 issued by the Executive Engineer, Provincial Division No.III, PWD, B&R Branch, Karnal, the letter of acceptance was cancelled and withdrawn and the Bid Security of 20 lakhs was forfeited.
6. It has to be mentioned that before re ceipt of the letter of acceptance, the respon dent had sent a letter dated 15-11-2008 in forming the Executive Engineer that the respondent was not interested in the work and, therefore, the amount of Bid Security deposited on 19-9-2008 may be refunded. However, the appellants did not consider or act upon the said letter dated 15-11-2008 of the respondent, as the respondent had agreed to keep its bid open for acceptance upto 90 days after the last date of receipt of bid and the said period of 90 days had not expired. In this connection, it has also to be mentioned that the letter of accep tance dated 26-11-2008 was issued to the respondent before the expiry of the above-mentioned period of 90 days.
7. After cancellation of the letter of ac ceptance issued to the respondent and af ter expiry of the above-mentioned period of 90 days on 17-12-2008, the Executive Engineer vide Bid Notice No.5160, dated 31-12-2008 re-invited bids for the collec tion of toll at toll point on the Bridge over river Yamuna on Karnal-Meerut Road. The respondent again participated in the bid, offering an amount of 4,94,91,
810. It may be noted that the amount offered by the respondent in the subsequent bid was less than its offer in the first bid with a dif ference of 3.03 crores. Since the respondent's bid was the highest bid among the bids submitted pursuant to the Bid No tice dated 31-12-2008, a letter of acceptance was issued to the respondent on 6-2-2009. The respondent deposited the security amount and the first instalment in terms of the said letter of acceptance.
8. After the second letter of acceptance dated 6-2-2009 was issued to the respon dent, the respondent on 7-2-2009 filed C.W.P. No.2266 of 2009 in the Punjab and Haryana High Court praying for quashing the first letter of acceptance dated 26-11-2008 of the Executive Engineer and the Memo No.5029, dated 17-12-2008 can celling the said letter of acceptance and forfeiting the Bid Security of 20 lakhs. Even though the appellants opposed the grant of prayers in the writ petition, a Di vision Bench of the High Court vide order dated 7-7-2009 allowed the writ petition quashing the letter of acceptance dated 26-11-2008 and the Memo dated 17-12-2008 and also directed the Executive Engineer (appellant No.5) to refund the Bid Security amount of 20 lakhs to the respondent within two months from the date of receipt of a copy of the order. Ag grieved by the said order dated 7-7-2009 passed by the High Court in C.W.P. No.2266 of 2009, the respondents in the writ petition have filed this appeal.
9. We have considered the pleadings in the case, the submissions made by the learned senior counsel for the parties and the materials placed on record.
10. For allowing the writ petition, the only reason stated by the High Court is that, since the writ petitioner (respondent herein) had withdrawn its offer before it was ac cepted, there could be no acceptance of the offer and there could not be any conse quence of the petitioner not honouring the commitment. However, we cannot agree with the view taken by the High Court. It is true that as per section 5 of the Indian Contract Act, 1872 (hereinafter referred to as "the Act"), a proposal may be revoked at any time before the communication of its acceptance is complete as against the proposer. It is also true that before receipt of the letter of acceptance dated 26-11-2008, the respondent had sent a let ter dated 15-11-2008 withdrawing its of fer. However, admittedly, in paragraph 8 of the written offer/bid, the respondent had agreed to keep the bid open for acceptance upto 90 days after the last date of receipt of bid. The respondent had also agreed that it shall be bound by the communication of acceptance of the bid dispatched within the aforesaid period of 90 days. Hence, the re spondent could not have withdrawn the bid before the expiry of the period of 90 days. It is not disputed that the acceptance of the respondent's bid was communicated to the respondent within the said period of 90 days. Therefore, the respondent was bound by the said acceptance of the bid, despite its withdrawal by the respondent in the meanwhile. In paragraph 10 of the offer/bid, the respondent had also agreed that the full value of the Bid Security would be for feited without prejudice to any other light or remedy available to the Executive En gineer or his successor-in-office or his rep resentative, should the respondent with draw or modify its offer/bid during the pe riod of bid validity (90 days) or extended validity period. Since the respondent with drew its offer during the period of bid va lidity in violation of the above-mentioned agreement in paragraph 8 of the offer/bid, the full value of Bid Security was liable to be forfeited in terms of the agreement con tained in paragraph 10 of the offer/bid. Thus, even though under section 5 of the Act a proposal may be revoked at any time before the communication of its acceptance is complete as against the proposer, the re spondent was bound by the agreement con tained in its offer/bid to keep the bid open for acceptance upto 90 days after the last date of receipt of bid and if the respondent withdrew its bid before the expiry of the said period of 90 days the respondent was liable to suffer the consequence (i.e. for feiture of the full value of Bid Security) as agreed to by the respondent in paragraph 10 of the offer/bid. Under the cover of the provisions contained in section 5 of the Act, the respondent cannot escape from the obligations and liabilities under the agree ments contained in its offer/bid. The right to withdraw an offer before its acceptance cannot nullify the agreement to suffer any penalty for the withdrawal of the offer against the terms of agreement. A person may have a right to withdraw his offer, but if he has made his offer on a condition that the Bid Security amount can be forfeited in case he withdraws the offer during the period of bid validity, he has no right to claim that the Bid Security should not be forfeited and it should be returned to him. Forfeiture of such Bid Security amount does not, in any way, affect any statutory right under section 5 of the Act. The Bid Security was given by the respondent and taken by the appellants to ensure that the offer is not withdrawn during the bid va lidity period of 90 days and a contract comes into existence. Such conditions are included to ensure that only genuine par ties make the bids. In the absence of such conditions, persons who do not have the capacity or have no intention of entering into the contract will make bids. The very purpose of such a condition in the offer/bid will be defeated, if forfeiture is not per mitted when the offer is withdrawn in vio lation of the agreement.
11. In taking the above view, we are sup ported by the decision of this Court in Na tional Highways Authority of India v. Ganga Enterprises and another [(2003) 7 SCC 410] : (AIR 2003 SC 3823 : 2003 AIR SCW 4381) which was rendered in a similar case. In the said case, the appellant, National Highways Authority of India, by a notice, called for tenders by 31-7-1997 for collec tion of toll on a portion of a particular high way. The notice provided that toll plazas would be got completed by the appellant and handed over to the selected enterprise. The notice required the bidders to furnish: (i) a bid security in a sum of 50 lakhs in the form of a bank draft or bank guarantee, and (ii) a performance security in the form of a bank guarantee of 2 crores. The bid security was liable to forfeiture in case the bidder withdrew his bid during the valid ity period of the bid or failed within the specified period to furnish the performance security and sign the agreement. The bid was to remain valid for a period of 120 days after the last date of bid submission. In terms of the tender document, the respon dent-firm gave its bid or offer and furnished a bank guarantee in a sum of 50 lakhs. It was an "on-demand bank guarantee" stat ing that it could be enforced on demand if the bidder withdrew his bid during the pe riod of bid validity or failed to furnish the performance security or failed to sign the agreement. While the validity period of the bid was to end on 28-11-1997, the respon dent withdrew its bid on 20-11-1997 and did not furnish the performance guarantee. Therefore, the appellant although found the respondent to be the highest bidder and ac cepted its offer on 21-11-1997, encashed the bank guarantee for 50 lakhs. The re spondent then filed a writ petition in the High Court for refund of the amount. The High Court formulated two questions viz.: (a) whether the forfeiture of security de posit was without authority of law and without any binding contract between the parties and also contrary to section 5 of the Contract Act; and (b) whether the writ petition was maintainable in a claim aris ing out of a breach of contract. Without considering Question (b), the High Court allowed the writ petition on the ground that the offer was withdrawn before it was ac cepted and thus no completed contract had come into existence. The High Court ob served that in law a party could always withdraw its offer before acceptance. Therefore, it held that the invocation and encashment of the bank guarantee was il legal and void and was liable to be set aside. The appellant then approached the Supreme Court. Allowing the appeal, this Court held as follows:-- "In our view, the High Court fell in er ror in so holding. By invoking the bank guarantee and/or enforcing the bid secu rity, there is no statutory right, exercise of which was being fettered. There is no term in the contract which is contrary to the provisions of the Indian Contract Act. The Indian Contract Act merely provides that a person can withdraw his offer before its acceptance. But withdrawal of an offer, before it is accepted, is a completely dif ferent aspect from forfeiture of earnest/se curity money which has been given for a particular purpose. A person may have a right to withdraw his offer but if he has made his offer on a condition that some earnest money will be forfeited for not en tering into contract or if some act is not performed, then even though he may have a right to withdraw his offer, he has no right to claim that the earnest/security be re turned to him. Forfeiture of such earnest/security, in no way, affects any statutory right under the Indian Contract Act. Such earnest/security is given and taken to en sure that a contract comes into existence. It would be an anomalous situation that a person who, by his own conduct, precludes the coming into existence of the contract is then given advantage or benefit of his own wrong by not allowing forfeiture. It must be remembered that, particularly in Government contracts, such a term is al ways included in order to ensure that only a genuine party makes a bid. If such a term was not there even a person who does not have the capacity or a person who has no intention of entering into the contract will make a bid. The whole purpose of such a clause i.e. to see that only genuine bids are received would be lost if forfeiture was not permitted." We respectfully agree with the above view of this Court.
12. Hence, the High Court was not jus tified in quashing the letter dated 26-11-2008 accepting the bid of the respon dent and the letter dated 17-12-2008 for feiting the Bid Security amount of 20 lakhs. The appeal is allowed and the order dated 7-7-2009 passed by the High Court of Punjab and Haryana in C.W.P. No.2266 of 2009 is set aside. Consequently, the writ petition stands dismissed. There will be no order as to costs. M.W.A./6/SC-Ind. Appeal allowed.