CLC 2021

2021 PLP 915 (CLC)

EXECUTIVE ENGINEER, HIGHWAYS DIVISION MORO and 4 others — Applicants Versus NAZEER AHMED and others — Respondents

Jurisdiction / Court
Sindh (Sukkur Bench)
Decided Date
2020-August-27
Honorable Judges
N/A
Case Reference Summary (AEO Optimized)
Citation 2021 PLP 915 (CLC)
Forum / Court Sindh (Sukkur Bench)
Bench Members N/A
Parties EXECUTIVE ENGINEER, HIGHWAYS DIVISION MORO and 4 others — Applicants Versus NAZEER AHMED and others — Respondents
Primary Law (c) Land Acquisition Act (I of 1894), (b) Land Acquisition Act (I of 1894), (a) Civil Procedure Code (V of 1908)
💡 Quick Legal QA & Summary / سوال و جواب خلاصہ
Q1: What are the key laws and sections cited in 2021 PLP 915 (CLC)?

This judgment primarily cites: (c) Land Acquisition Act (I of 1894), (b) Land Acquisition Act (I of 1894), (a) Civil Procedure Code (V of 1908) as referenced in Pakistani case law index.

Q2: Which judicial bench decided the case 2021 PLP 915 (CLC)?

The case was heard and decided by the Sindh (Sukkur Bench) bench comprising: N/A.

Q3: What is the official citation format for this judgment on Pakistan Law Portal?

Cite this legal precedent as: 2021 PLP 915 (CLC) (EXECUTIVE ENGINEER, HIGHWAYS DIVISION MORO and 4 others — Applicants Versus NAZEER AHMED and others — Respondents). Read the full summary and cross-referenced laws free on Pakistan Law Portal.

Laws Cited

(c) Land Acquisition Act (I of 1894) (b) Land Acquisition Act (I of 1894) (a) Civil Procedure Code (V of 1908)

Representation

  • Ahmed Ali Shahani, Assistant Advocate General for Applicant.
  • Nemo. for Respondent.

Headnotes / Summary

Ss.97 & 115

Revision petition against preliminary decree

Maintainability

Limitation

"Case decided"

Scope

Petitioners / judgment-debtors did not prefer an appeal against the preliminary decree passed by the Appellate Court but, after five months when final decree was passed, they assailed both the decrees in revisional jurisdiction of the High Court

Contention of respondents/decree-holders was that assailing the preliminary decree in revisional jurisdiction was neither maintainable nor within time

Held, that S.97 of the Civil Procedure Code, 1908 ,which precluded a party from disputing the correctness of a preliminary decree in an appeal from the final decree when no appeal was preferred from the preliminary decree, did not put the same restriction on a revision application

Revision under S.115 of the Civil Procedure Code, 1908, was against a "case decided", however, that was not to say that a revision application could never be filed against a preliminary decree before the passing of a final decree, inasmuch as the terms of a preliminary decree might be a "case decided" within the meaning of S.115 of the Civil Procedure Code, 1908

Question, in the present case, related the very jurisdiction of the subordinate Court to decide the case , such question remained open in a revision from the final decree even though no revision application had been preferred from the preliminary decree

Revision petition in the present case was, thus, within time period of limitation.

Ss.9, 11, 18 & 52

Land acquired by the Government

Suit for compensation filed before civil court

Jurisdiction of civil court

Scope

Contention of the petitioners (Highways Division) was that plaintiffs/respondents ,instead of filing a claim for compensation before the Land Acquisition Officer, had approached civil court which had no jurisdiction to entertain the claim

Held, that the notice, in the present case, for inviting claims for compensation, pursuant to S.9 of the Land Acquisition Act, 1894, was issued 8 years after the land (including subject-property) was occupied by the Government

Said delayed notice was issued about one year after the institution of suit by the plaintiffs/respondents, however, even after disclosure of pendency of compensation proceedings (under the Land Acquisition Act, 1894) in the written statement filed by the petitioners, the plaintiffs did not file a claim for compensation before the Collector pursuant to S.9 of the Land Acquisition Act, 1894 nor they moved under S.18 of the said Act, 1894 for making a reference against the award to the Court designated for the purpose

Acquisition proceedings remained unchallenged , therefore, the suit of the plaintiffs could not be said to be one envisaged under S.52 of the Land Acquisition Act, 1894, to question anything done in pursuance of the said Act

Decree passed by the Appellate Court was without jurisdiction

High Court set aside the judgment, the preliminary decree and final decree passed by the Appellate Court and restored the judgment and decree passed by the Civil Court dismissing the suit of the plaintiffs

Revision was allowed, in circumstances.

S.18

Civil Procedure Code (V of 1908), S.9

Land acquired by the Government

Suit for compensation filed before the civil court

Plenary jurisdiction of civil court

Scope

Plaintiffs, in the present case, failed to invoke special jurisdiction of the designated Court under S.18 of Land Acquisition Act, 1894

Section 9 of Civil Procedure Code, 1908, contemplated an implied bar as to the general/plenary jurisdiction of the civil court to decide the plaintiffs' suit for compensation

Such implied bar could only be circumvented if the plaintiffs demonstrated that the case attracted one of the established exceptions to the ouster of the plenary jurisdiction of civil court, which was never asserted by the plaintiffs

Revision was allowed, in circumstances.

Judgment & Decree

ADNAN IQBAL CHAUDHRY J.

F.C. Suit No. 54/1993 filed by the Respondents / their predecessors (Plaintiffs) for compensation of land consumed in certain road construction projects, was dismissed by the learned Senior Civil Judge, Moro; however, in Civil Appeal No. 10/1999, the learned Additional District Judge, Moro, decreed the suit in part; hence this revision application by the Applicants (Defendants).

2. It was the case of the Plaintiffs that in 1972-73, the Government of Sindh constructed a road from Moro to Mithani (the 'first road project') which utilized part of the Plaintiffs' ancestral land in Survey No. 373 of Deh Manaheen, Taluka Moro;1 that in 1977-78,2 the Government constructed a road to village Puran (the 'second road project'), which utilized part of the Plaintiffs' land in Survey Nos. 349, 350 and 351 of Deh Manaheen; that again in 1993,3 the Government utilized the Plaintiffs' land in Survey Nos. 383, 385 and 782 of Deh Manaheen to construct the Nather Ditta Road4 (the 'third road project'). It was contended that time and again the Plaintiffs approached the Executive Engineer Highways, Moro, for compensation of said land, but in vain; hence the prayer for damages @ Rs.100,000/- per acre.

3. Officers of the Highways Division were arrayed as Defendants 1 to

3. The Land Acquisition Officer was arrayed as Defendant No.

4. The Province of Sindh was arrayed as Defendant No. 5 although it was wrongly sued through the Deputy Commissioner Naushahro Feroze. A written statement was filed by the Executive Engineer, Highways Division, Moro. The suit proceeded ex-parte against the Land Acquisition Officer and the Province.

4. It was the case of the Highways Division that while the said three road projects had been undertaken by them, the land for the same had been duly acquired by the Government under the Land Acquisition Act, 1894; that for acquiring the land for the first and second road projects in the years 1972-73 and 1977-78 respectively, the Highways Division had made the prescribed payment to the Acquisition Office B&R, Hyderabad, who in turn had released compensation to the affected khatedars, albeit in view of a higher rate subsequently recommended by the Deputy Commissioner Nawabshah, the matter with regards to additional compensation was still pending; that the Plaintiffs had never approached the Land Acquisition Officer for compensation; and that the third road project was constructed under a Senator Scheme sponsored under the Tameer-e-Watan Program. It was further contended that Survey No. 373 in Deh Manaheen claimed by the Plaintiffs, had never been utilized in the road projects.

5. By judgment and decree dated 12-11-1998, the trial court dismissed the suit holding that the Plaintiffs had failed to prove that in the years 1972-73 and 1977-78 they were owners of the Survey Numbers claimed by them; that village Form-XV produced by the Plaintiffs was not reliable evidence of ownership of the land in question as the same was issued in the year 1980; and that in any case, the remedy of the Plaintiffs for compensation was before the authority/forum designated under the Land Acquisition Act, 1894.

6. On the appeal of the Plaintiffs (Respondents herein), the appellate court passed judgment for the Plaintiffs holding that village Form-XV was sufficient evidence of the Plaintiffs' ownership of Survey Nos. 349, 350 and 351; that the evidence showed that land in Survey Nos. 349, 350 and 351 had been acquired by the Government for constructing a road to village Puran (second road project) for which the Plaintiffs were not compensated; and by a preliminary decree dated 19-05-1999, the appellate court proceeded to appoint a commissioner to determine the rate of land and the area acquired. On receipt of the commissioner's report, the appellate court then passed a final decree dated 23-10-1999 awarding compensation to the Plaintiffs @ Rs.100,000/- per acre to the extent of 4-07 acres of land in Survey Nos.349, 350 and 351 of Deh Manaheen, Taluka Moro, i.e. a sum of Rs.417,500/-.

7. Thus, while the trial court held that the Plaintiffs had not been able to prove ownership of any part of the land claimed in the suit, the appellate court held that the Plaintiffs had been able to prove ownership of least of Survey Nos. 349, 350 and

351. The Plaintiffs did not appeal the denial of relief for the other Survey Numbers. Therefore, it is only Survey Nos. 349, 350 and 351 of Deh Manaheen that are relevant to this revision.

8. The learned A.A.G. Sindh submitted that suit for compensation for land acquired in 1972-73 and 1977-78 was time-barred; that the appellate court mis-read the evidence in holding that the Plaintiffs had proved ownership to the land in question; and that, since the land had been acquired under the Land Acquisition Act, 1894, and since the Plaintiffs had not approached the authority/forum under the said Act for compensation, the civil court could not have exercised general jurisdiction to decide the question of compensation as so held in Abdul Manan v. Chairman WAPDA (1990 CLC 1377).

9. Heard the learned AAG Sindh and perused the record.

10. In their objections to this revision, the Respondents (Plaintiffs) have taken the plea that the revision is time-barred. I advert to that objection first. The preliminary decree passed by the appellate court is dated 19-05-1999. The final decree is dated 23-10-1999. The revision is directed against both. From the final decree, this revision application filed on 20-01-2000, on the 89th day, is within the limitation of 90 days. However, if separate limitation is computed for the preliminary decree, then to that extent the revision is delayed by 156 days. But then, section 97, C.P.C. which precludes a party from disputing the correctness of a preliminary decree in an appeal from the final decree when no appeal was preferred from the preliminary decree, does not put the same restriction on a revision application. Rather, under section 115, C.P.C., a revision is against a 'case decided'. However, that is not to say that a revision application can never be filed against a preliminary decree before the passing of a final decree, inasmuch as the terms of a preliminary decree may well be a 'case decided' within the meaning of section 115, C.P.C.5 Nevertheless, in my view, where the question is to the very jurisdiction of the sub-ordinate court to decide the case, such question remains open in a revision from the final decree even though no revision application had been preferred from the preliminary decree.6. Thus, this revision is within limitation.

11. I now advert to the grounds of the revision. It appears that to hold that the Plaintiffs had proved ownership to Survey Nos. 349, 350 and 352 of Deh Manaheen, the learned appellate court relied on village Form-XV produced by the Plaintiffs. Suffice to observe that in the absence of any document / entry to show title of the Plaintiffs' predecessors through whom the Plaintiffs claimed to have inherited Survey Nos. 349, 350 and 352, village Form-XV on its own was hardly proof of ownership to the said land.

12. Be that as it may, like the trial court the appellate court too found that the land claimed by the Plaintiffs in Survey Nos. 349, 350 and 351 had in fact been acquired by the Government under the Land Acquisition Act, 1894 for the public purpose of constructing a road. The learned AAG Sindh has also filed a copy of notice dated 27-12-1994 issued under section 9 of the Land Acquisition Act, and the award dated 18-05-1995 made under section 11 thereof in respect of land acquired for constructing the road to village Puran, Taluka Moro, which included the subject Survey Nos. 349, 350 and

351. From the award it appears that while the said land was occupied by the Government in the year 1986, the notice inviting claims for compensation pursuant to section 9 of the Land Acquisition Act was delayed until 1994, after the suit had been filed in 1993. However, even after the suit, when compensation proceedings under the Land Acquisition Act were disclosed in the written statement of the Highways Division, the Plaintiffs did not file a claim for compensation before the Collector pursuant to section 9 of the Land Acquisition Act, nor did they move under section 18 thereof for making a Reference against the award to the court designated for such purpose. The acquisition proceedings remained unchallenged. Therefore, the suit of the Plaintiffs cannot be said to be one envisaged under section 52 of the Land Acquisition Act to question anything done in pursuance of the said Act.

13. In the circumstances of the case, given the failure of the Plaintiffs to invoke the special jurisdiction of the designated court under section 18 of the Land Acquisition Act, 1894, there was an implied bar, as contemplated under section 9, C.P.C., to the general / plenary jurisdiction of the civil court to decide the Plaintiffs' suit for compensation. Such implied bar could only be circumvented if the Plaintiffs demonstrated that the case attracted one of the established exceptions to the ouster of the plenary jurisdiction of a civil court,7 which, as already noted, was not the case set-up by the Plaintiffs.

14. For the foregoing reasons, the decree passed by the appellate court awarding compensation for land acquired under the Land Acquisition Act, 1894, was without jurisdiction. Accordingly, this revision application is allowed; the judgment, the preliminary decree and the final decree passed by the appellate court in Civil Appeal No. 10/1999 are set-aside; and the judgment and decree passed by the trial court dismissing F.C. Suit No. 54/1993 is restored. MQ/E-2/Sindh Revision allowed.