PLD 2003

P L D 2003 Lahore 714 (PLP)

HYUNDAI-HIDCO-HAKAS JOINT VENTURE — Petitioner Versus WATER AND POWER DEVELOPMENT AUTHORITY — Respondent

Jurisdiction / Court
High Court
Decided Date
2003-June-2
Honorable Judges
N/A
Case Reference Summary (AEO Optimized)
Citation P L D 2003 Lahore 714 (PLP)
Forum / Court High Court
Bench Members N/A
Parties HYUNDAI-HIDCO-HAKAS JOINT VENTURE — Petitioner Versus WATER AND POWER DEVELOPMENT AUTHORITY — Respondent
Primary Law (a) Constitution of Pakistan (1973), (e) Constitution of Pakistan (1973), (b) Constitution of Pakistan (1973)
💡 Quick Legal QA & Summary / سوال و جواب خلاصہ
Q1: What are the key laws and sections cited in P L D 2003 Lahore 714 (PLP)?

This judgment primarily cites: (a) Constitution of Pakistan (1973), (e) Constitution of Pakistan (1973), (b) Constitution of Pakistan (1973) as referenced in Pakistani case law index.

Q2: Which judicial bench decided the case P L D 2003 Lahore 714 (PLP)?

The case was heard and decided by the High Court bench comprising: N/A.

Q3: What is the official citation format for this judgment on Pakistan Law Portal?

Cite this legal precedent as: P L D 2003 Lahore 714 (PLP) (HYUNDAI-HIDCO-HAKAS JOINT VENTURE — Petitioner Versus WATER AND POWER DEVELOPMENT AUTHORITY — Respondent). Read the full summary and cross-referenced laws free on Pakistan Law Portal.

Laws Cited

(a) Constitution of Pakistan (1973) (e) Constitution of Pakistan (1973) (b) Constitution of Pakistan (1973)

Representation

  • Raza Kazim for Petitioner:
  • Tariq Kamal Qazi for Respondent.
  • He further submitted that payments made to the petitioner cannot be recovered by the respondent under WAPDA Rules and Regulations and in fact, there are none. The sole object of the respondent's decision is to recover the payments made to the petitioner for its time-related claim through encashment of its Bank guarantees and to compel the petitioner to give up its valid claims of more than US$ 36 million out of which about US$ 18 million have been verified by the engineer. Learned counsel urged that WAPDA is proceeding against the properties of the petitioner which are no longer securities. Respondent holds the securities in trust for petitioner. Withholding of the same is the violation of Articles 4, 24 and 260 of the Constitution of Islamic Republic of Pakistan. WAPDA as a Public Authority, is bound to act reasonably and fairly. He referred to sections 21 and 24-A of the General Clauses Act. WAPDA acts are motivated by malice. Learned counsel urged that the presence of arbitration clause in the contract does not debar the Constitutional remedy. The respondent is bound to release the bank guarantees. Reliance was placed on Messrs Gadoon Textile Mills and 814 others v. WAPDA and others (1997 SCMR 641), Murree Brewery Co. Ltd. v. Pakistan through Secretary to Government of Pakistan, Works Division and 2 others (PLD 1972 SC 279; The Federation of Pakistan through the Secretary, Establishment Division, Government of Pakistan, Rawalpindi v. Saeed Ahmad Khan and others (PLD 1974 SC 151), Messrs Airport Support Services v. The Manager, Quaid-e-Azam International Airport, Karachi and others (1998 SCMR 2268), Anjuman-e-Ahmadiyya, Sargodha v. Deputy Commissioner, Sargodha and another (PLD 1966 SC 639), Shaukat Ali v. Secretary, Industries and Mineral Development, Government of Punjab, Lahore and 3 others (1995 MLD 123), Asif Iqbal v. Karachi Metropolitan Corporation and 2 others (PLD 1994 Karachi 60), Federal Government Employees Housing Foundation through Director General, Islamabad v. Muhammad Akram Alizai, Deputy Controller, PBC, Islamabad (PLD 2002 SC 1079) and Abdul Rauf and others v. Capital Development Authority, Islamabad (1988 MLD 1523).

Headnotes / Summary

Art. 199

Constitutional petition

Contract for construction of civil works

Arbitration clause

Contractor (petitioner) sought release of security documents/guarantees after substantial performance of contract and completion of works

Employer disputed decisions of "Engineer" (appointed for purposes of contract) regarding certification and payment of money against contractor's claim

Validity

Factual controversy existed between parties, which could not be resolved by High, Court in exercise of Constitutional jurisdiction

Dispute between employer and contractor in connection with or arising out of contract of execution of works according to conditions of contract would be referred to and settled by "Engineer" and subject to arbitration, his decision would be final

Employer had not accepted decision of Engineer and had invoked arbitration clause of the contract

Despite satisfaction, approval or certification by engineer, employer could show that work was not in accordance with contract-- Employer could not become a Judge in his own cause without recourse to arbitration and ask for encashment of Bank guarantees, which would amount to forfeiture of contractor's property without getting dispute adjudicated first

Contractor had to make colossal payment to Bank after notice of encashment of Bank guarantees by employer

Such unlawful pressure exerted on contractor was not a normal commercial or permissible pressure, but same had constituted improper threat and conduct in coercing him to make disputed payment to employer and keep guarantees intact

Right of employer to encash Bank guarantees not disputed, but employer had not acted fairly and reasonably- in such , case

Such fact could not be decided in Constitutional petition, which was dismissed by High Court.

Art. 199

Factual controversy

Could not be resolved by High Court in exercise of Constitutional jurisdiction.

Art. 199

National Accountability Ordinance (XVIII of 1999), S.9-- Loss to public exchequer caused by public functionaries

Observation of High Court

Contract for construction of Chashma Hydropower Electric Project

Delay of 1129 days in completion of project due to mis-management and inefficiency of WAPDA. and ,concerned Authorities-- Original evaluated cost of project was Rs.10,557 million, which had increased to Rs.17,822 million on account of such delay

Citizens of country had been made to incur and suffer an extra cost of Rs.7265 million

Neither responsibilities had been fixed nor any action had been taken against guilty nor National Accountability Bureau had initiated any inquiry.

Judgment & Decree

Clause 62.1--Approval and Issuance of Defects Liability Certificate. Clause 10.1.17 and 60.4.C--Additional Cost of the Continuing Provisions of Contract Securities. Reference is made to your Letter No.3242-26199 dated June 11, 2002 conveying the Engineer's decision on the subject-matter. WAPDA does not agree with the subject cited Engineer's decision and has opted for Arbitration in accordance with Clause 67 of Conditions of Civil Works Contract Part-11. This is for your information record and further necessary action, if any, please.". Again vide letter dated 2-9-2002 it was stated as under:-- Subject: Civil Works Contract--Engineer's decisions in accordance with Clause 67.A Employers Rejection of Engineer's Interim Evaluation Report for Section A--General Expenses. Reference is made to CGC Letter No.3242-26258 dated June 21, 2002 conveying the Engineer's decisions on the subject-matter. WAPDA does not agree with this Engineer's decisions and has opted for arbitration in accordance with Contract Provisions. This is for your information, record and further necessary action, if any, please." Learned counsel for the respondent has placed on record a chart of the dispute about the factual controversy between the parties which is reproduced as under:

1. DLC (DEFECT LIABILITY CERTIFICATE) 28-2-2002 Proper date according to contractor. 13-2-2002 WAPDA's claim regarding correct date. 16-4-2002 Contractor sought Engineer's decision under clause 67.A. 11-6-2002 Decision 31-7-2002 Arbitration Notice.

2. TOC (TAKING OVER CERTIFICATE) Substantial Completion Refund of 50% Retention Money (FCY) and 25 % Retention Money LCY + FCY. 8-11-2000 According to Contractor [+Engineer] 13-2-2001 According to WAPDA. Approved with 97 days LDs. 21-3-2002 Contractor sought Engineer's decision pursuant to clause 67-A 29-8-2002 Engineer's decision 4-6-2002 Notice of Arbitration by WAPDA 50% Unpaid RM was adjusted against on account of payment of USD 5,485,3781.48 50%RM=USD 1,790,370.

3. ON A/C PAYMENT USD 5,485,381.48. 21-3-2002 Contractor sought Engineer's decision under 67-A. 29-5-2002 Decision of Deputy Engineer 4-9-2002 Arbitration Notice by WAPDA After adjustments against payment for Works and Retention Money. USD 2,505,463.28 Principal, and USD 601,408.34 Interest. USD 3,106,871.62 Paid in excess.

4. CLAIM SUBMISSION NO. 6, SECTION A GENERAL EXPENSES. 18-5-2002 Claim rejected for Rs.62,911,860. $5,155,321. 30-5-2002 Contractor sought Engineer's decision under Clause 67-A 21-6-2002 Decision of Engineer 22-8-2002 2-9-2002 Arbitration Notice by WAPDA. The letter of the respondent dated July 7, 2000 reads as under:-- "However on-account payment duly recommended by CGC would be made to M/s. Hyundai/Hidco-Kakas JV after approval of WAPDA Authority. If subsequently CGC consider that M/s. Hyundai/Hidco-Hakas JV were not entitled to such payment, then WAPDA would reserve the right to recover such on-account payment from M/s. Hyundai/Hidco-Hakas JV." This leaves not a scintilla of doubt in my mind that the factual controversy does exist between the parties which cannot be resolved in the exercise of 8 Constitutional jurisdiction by this Court. The Hon'ble Supreme Court of Pakistan in the case of Messrs Airport Support Services v. The Airport Manager, Quaid-e-Azam International Airport, Karachi and others (supra) has stated as under:-- "It has consistently been held that while routine contractual disputes between private parties and public functionaries are not open to scrutiny under the Constitutional jurisdiction, breaches of such contracts, which do not entail inquiry into or examination, of minute or controversial questions of fact, if committed by Government, semi-Government or Local Authorities or like controversies if involving dereliction of obligations, flowing from a statute, rules or instructions can adequately be addressed for relief under that jurisdiction. Further a contract, carrying elements of public interest, concluded by functionaries of the State, has to be just, fair, transparent, reasonable and free of any taint of mala fides, all such aspects remaining open for judicial review. The rule is founded on the premises that public functionaries, deriving authority from or under law, are obligated to act justly, fairly, equitably, reasonably, without any element of discrimination and squarely 'within the parameters of law, as applicable in a given situation. Deviations if of substance, can be corrected through appropriate orders under Article 199 of the Constitution. In such behalf even where a contract, pure and simple, is involved, provided always that public element presents itself and the dispute does not entail evidentiary facts of a disputed nature, redress may be provided. " In the case of Amin Fabrics Limited, Karachi v. Pakistan Agricultural Storage and Services Corporation Ltd. (PASSCO), Lahore and another (PLD 1999 Lahore 313), Karamat Nazir Bhandari, J., as he then was, observed as under:-- "As noted by me, in the case of N.T.M., not much difficulty arises in cases where contract is rooted in some statutory provisions/rules/instructions. Cases of leases and contracts under the Punjab Local Government Ordinance, 1979, Petroleum Act, 1934 Mining Concession Rules, leases under Colonization of Government Lands Act, 1912 and host of schemes claims framed thereunder can be referred to as the cases falling in this category. The difficulty arises in cases of pure and simple commercial and mercantile contracts, free from any constraints of statutory provisions/rules. " Under clause 67.A of the conditions of contract the dispute between the Employer and the Contractor in connection with, or arising out of the contract, or the execution of the works whether during the progress of the works or after their completion shall be referred to and settled by the engineer. Subject to arbitration his decisions in respect of every matter so referred shall be final and binding upon the Employer and the Contractor. The respondent has invoked the arbitration clause 67.A and rightly so. In my view if the Employer can show, despite the satisfaction approval or certification by the engineer that the work nevertheless is not in accordance with the contract, he is not precluded from invoking the arbitration clause. It is yet to be seen that the certificate or satisfaction of the engineer is final and binding on the Employer and the Contractor. In view of the above discussion I do not consider it necessary to examine the rest of plethora of case-law cited by both the parties.

4. There is another aspect of the matter that though the respondent has not accepted the decisions of the engineer and has invoked the Arbitration clause 67.A of the conditions of contract, yet has not acted fairly in calling upon the banks to encash the bank guarantees. Learned counsel for the respondent admitted that there are no WAPDA Rules and Regulations for forfeiture of the Contractor's securities. He stated at the bar that WAPDA has decided to go to arbitration and will not invoke the clause authorising encashment of bank guarantees before the resolution of the dispute through arbitration. Clause 67.A of the contract clearly states that the dispute between the Employer and the Contractor in connection with or arising out of contract, or the execution of work shall in the first place be referred to and settled by the engineer who shall within a period of 90 days, after being requested by cither party to do so give written notice of his decision to the employer and the Contractor. Subject to Arbitration the decision of the Engineer shall be final and binding upon the Employer and the Contractor and shall forthwith be given effect to by the Employer and the Contractor. The respondent-Employer has not agreed with the decisions of the engineer and has chosen to go to arbitration under the aforementioned clause. Without having recourse to arbitration, the Employer could not become a judge in his own cause and ask for encashment of the bank guarantees which would have amounted to forfeiture of the property of the petitioner without getting the dispute adjudicated first. The petitioner has placed on record a document showing that he had to pay US$ 7.4 million to the banks after the notice of encashment of the bank guarantees by the respondent. The petitioner appears to have suffered immensely in its credit rating before its guarantors. It had to make colossal payment. The disposition made by the respondent, towards the petitioner put him under a great financial risk. In my view unlawful pressure was exerted on him. This in fact amounted to economic coercion. The respondent acted like a gunman who actually helps himself to his victim's wallet. The coercive nature of the threat, though it was withdrawn thrice, was so powerful that the petitioner had to deposit $ 7.4 million with its guarantors. In my judgment it constituted an improper threat and conduct in coercing the petitioner for making the disputed payments to the respondent and keep the guarantees intact. It does not appear normal commercial pressure or permissible pressure to exert. I am not disputing the right of the respondent to encash the bank guarantees but in all fairness the respondent has not acted fairly and reasonably in the particular circumstances of the case. Unfortunately, this fact again cannot be decided in this Constitutional petition. Lastly I would like to observe that according to the record placed before this Court it transpires that original evaluated cost of the project was Rs.10,557 million. There is a delay of 1129 days (three years and thirty four days) in the completion of the project. The price of the project was increased to Rs.17822 million, thus costing the exchequer extra Rs.7265 million. The project clearly reflects inefficiency of WAPDA and the authorities concerned. The country has suffered a colossal loss of Rs.7265 million. ex facie the contract speaks volumes for the mismanagement and inefficiency of the authorities concerned in the implementation of the project. The responsibilities have not been fixed nor any action has been taken against the guilty. Even NAB has not initiated any inquiry. Every body seems to be complacent. The citizens of this country have been made to incur and suffer an extra cost as aforementioned. No body seems to be responsible.

5. The upshot of the above discussion is that this petition has no merit and is dismissed leaving the parties to bear their own costs. S.A.K./H-151/L Petition dismissed.